Invest in Our Economy


                                Goal 1: Enhance Economic Impact Through Development and
                            Redevelopment Efforts, Partnerships, and Investment Opportunities
                                Objective 1: Foster Development and Redevelopment in Targeted Areas
                        Project                     Performance Measure(s)           City Service Team (Department)
             IOE   East Arlington Recreation     Overall Satisfaction of Project Management   Shared Services (AM) and
             1.1.2  Center/Library           Project Completion on Time and at Budget   Neighborhood Services (Library
                                              Citizen Satisfaction with Overall Library and   and Parks)
                                              Parks Services
             Summary:
                                                                  Milestone            Estimated      Actual
             Working collaboratively with other city                                  Completion    Completion
             departments, as well as with architectural and   Initial Project        Sept. 2015   Sept. 2015
             construction management professionals, to build a   Schedule/Development Phase
             new East Arlington Recreation Center and Library   Architect/Engineer RFQ    Aug. 2015   Aug. 2015
             Complex.                                     Architect/Engineer Selection   Nov. 2015   June 2016
                                                          Process
             Update:                                      Design Development         Mar. 2018    Mar. 2018
                   th
             In the 4  quarter of FY 2020 the construction was   Finalize construction   Fall 2018   Dec. 2018
             near 92% completion. Exterior work was on going   documents
             with grass and plant materials being installed.   Construction contract award   Fall 2018   Feb. 2019
             Interior finishes were wrapping up and furniture   Permit Process       Fall 2018    Jan. 2019
             was in the process of being delivered. A Certificate   Construction begins    Fall 2018   Mar. 2019
             of Occupancy will be applied for in October.   Finalize selection of furniture   Fall 2019   Dec. 2019
             Demolition of Hugh Smith Recreation Center will
                                                          and equipment
             begin in late October.                       Recreation Center          Oct. 2020
                                                          construction complete

                                                          Move In – Recreation Center    Oct. 2020
                                                          Library construction complete  Oct. 2020
                                                          Move In – Library          Oct. 2020



































                                                             28