Page 381 - FY 2009 Proposed Budget
P. 381

Invest in Our Economy


                                Goal 1: Enhance Economic Impact Through Development and
                            Redevelopment Efforts, Partnerships, and Investment Opportunities
                                Objective 1: Foster Development and Redevelopment in Targeted Areas
                          Project                    Performance Measure(s)        City Service Team (Department)
             IOE   South Cooper Street Master   Completion of Plan               Shared Services (Office of Strategic
             1.1.4  Plan                                                         Initiatives)
             Summary:
                                                                     Milestone         Estimated     Actual
             The South Cooper Street corridor between Mitchell                         Completion  Completion
             and Bardin has not ever been the focus of a corridor   Issue Request for Proposals   Sept. 2019   Oct. 2019
             redevelopment plan.  Originally developed between   Select and Contract with   Nov. 2019   Dec. 2019 –
             40‐50 years ago, the corridor needs attention to   Consultant                         Jan. 2020
             address design standards, retail and commercial mix,   Draft Plan         July 2020
             vacancies, and underutilized property.  The Office of   Final Plan        Nov. 2020
             Strategic Initiatives will undertake a year‐long master
             planning effort to develop strategies for
             redevelopment and reinvigoration of the corridor.

             Update:
             This project has restarted after being put on hold due
             to the COVID‐19 pandemic. A new contract was
             executed in August 2020 to resume the project with
             the original consultant team and the Existing
             Conditions Analysis is complete. The Advisory
             Committee met for the first time in September 2020.
             The revised schedule anticipates the draft plan
             completion in January 2021 and final plan adoption in
             May 2021.