Invest in Our Economy
Goal 1: Enhance Economic Impact Through Development and
Redevelopment Efforts, Partnerships, and Investment Opportunities
Objective 1: Foster Development and Redevelopment in Targeted Areas
Project Performance Measure(s) City Service Team (Department)
IOE Redevelopment of Overall Satisfaction of Project Management Shared Services (AM) and
1.1.1 Texas Rangers Golf Project Completion on Time and at Budget Neighborhood Services (Parks)
Course Citizen Satisfaction with Overall Quality of Parks
and Recreation Programs and Classes
Summary:
Milestone Estimated Actual
The redevelopment of Texas Rangers Golf Course is Completion Completion
one of many redevelopment efforts in North Phase 1 construction June 2016 July 2016
Arlington. The golf course master plan approved by drawings complete
City Council includes a complete renovation of the Phase 1 project bid Aug. 2016 Oct. 2016
golf course, new clubhouse and maintenance Phase 1 construction Nov. 2016 Jan. 2017
building, expanded driving range and a practice begins
facility. The golf course improvements will provide a Phase 2 construction June 2017 June 2017
high‐quality playing experience at an affordable price drawings complete
point for Arlington residents while providing another
Phase 2 project bid July 2017 Aug. 2017
destination for visitors to the Entertainment District. Phase 2 construction Sept. 2017 Sept. 2017
contract award
The project is constructed in the following phases: Phase 2 construction Sept. 2017 Nov. 2017
Phase 1 – Golf Course construction begins
Phase 2 – Maintenance, on‐course restrooms; Phase 3 construction Oct. 2017 Oct. 2017
temporary clubhouse and parking lot drawings complete
Phase 3 – Clubhouse
Phase 1 construction Nov. 2017 Oct. 2017
Phase 3, the Clubhouse, is the only phase remaining complete
Phase 3 project bid Nov. 2017 Nov. 2017
to complete. The estimated completion timeframe
Phase 3 construction Dec. 2017 Dec. 2017
for this phase was revised from July 2019 to
contract award
December 2019 due to rebidding the construction
contract to keep the cost within budget. In Phase 3 construction Mar. 2018 Mar. 2018
begins
December, the completion date was extended until
June 2020 due to weather and changes in the work. Phase 2 construction Aug. 2018 Apr. 2019
complete
Update: Golf course grand Sept. 2018 May 2019
In the 4 quarter of FY 2020, the contractor was opening
th
approximately 95% complete with the club house. Phase 3 construction Nov. 2020
The only items remaining are some of the flooring, complete
kitchen and bar equipment and completion of patio Overall project Nov. 2020
areas. A punch list walk is scheduled for the week of completion
October 29th along with final inspections. A
Certificate of Occupancy will be applied for the week
of November 2, 2020.