Page 374 - FY 2009 Proposed Budget
P. 374

Enhance Regional Mobility


                          Goal 2: Plan, Manage, and Maintain Public Transportation Infrastructure
                           Objective 1: Optimize Effectiveness and Efficiency of Existing Transportation System
                       Project                   Performance Measure(s)           City Service Team (Department)
             ERM   IH‐30 and SH‐360      Overall satisfaction with the management   Economic Development and Capital
             2.1.2  Interchange          of traffic flow during peak hours     Investment (PWT)
             Summary:

             The purpose of this project is to improve traffic safety   Milestone    Estimated       Actual
             and reduce traffic congestion at the interchange of                    Completion     Completion
             Interstate 30 and State Highway 360.  Formerly a toll   Package A Construction   Spring 2022
             road loop interchange, the new infrastructure will   Package B Construction   Spring 2022
             include main lane improvements and direct       Package C Construction   Pending
             connection ramps to each facility.              Package D Construction   Pending
                                                             Package E Construction   Summer 2020
             This project is split into the following five
             construction phases:
                   Package A: Reconstruction of the Six Flags
                    Drive Bridge over IH‐30
                   Package B: IH‐30/SH‐360 interchange
                    improvements
                   Package C: Great Southwest Industrial
                    District railroad bridge crossing just south of
                    Randol Mill Road
                   Package D: Randol Mill Road interchange
                    improvements
                   Package E: Improvements from Abram
                    Street to IH‐20.

             Packages A and B will be bid as a joint project.

             Update:
             Texas Department of Transportation contractors
             continue to make progress on Packages A, B, and E.
             The estimated completion dated for Package E was
             moved from summer 2020 to December 2020.



























                                                             23