Enhance Regional Mobility


                          Goal 2: Plan, Manage, and Maintain Public Transportation Infrastructure
                                    Objective 2: Complete Construction Projects in a Timely Manner
                       Project                   Performance Measure(s)           City Service Team (Department)
             ERM   Street Rebuild Projects      Citizen perception of road condition as   Economic Development and Capital
             2.2.1                          "good" or "mostly good"            Investment (PWT)
                                           Lane Miles with Overall Condition Index
                                            (OCI) <50
             Summary:
                                                                     Project             Estimated   Actual Bid
             Capital street projects are funded with Street                              Bid Dates     Dates
             Bonds and are funded through inclusion in the   Abram Street (Cooper to Collins)   Nov. 2017   Feb. 2018
             annual capital budget.                       Timberlake Drive (Pioneer Pkwy to   Dec. 2017   Feb. 2018
                                                          Park Row Drive)
             The projects listed below are expected to begin   2017 Residential Rebuild; Phase 1   Feb. 2018   Mar. 2018
             construction during FY 2018.  Project milestones   Eden Road (US287 to Calender)   July 2018
             listed in the table will be updated as they occur   2018 CDBG Residential Rebuild   June 2018   June 2018
             during the year.                             (Belvedere)

             Update:
             Construction contract for the 2018 CDBG
             Residential Rebuild project was let in June.  Issues
             with Floodway on Eden Road Project need to be
             resolved before bidding.


                                                                                                  Estimated
                   Street Capital projects to be Advertised for Bid   Month Bid   Lane Miles   Actual Cost   Completion
                 Abram Street (Cooper to Collins)            Feb. 2018      3.3     $27.6 M     May 2020
                 Timberlake Drive (Pioneer Pkwy to Park Row Drive)   Feb. 2018   1.17   $5.9 M   Apr. 2019
                 2017 Residential Rebuild; Phase 1           Mar. 2018      2.04    $4.5 M      May 2019
                 2018 CDBG Residential Rebuild (Belvedere)   June 2018      0.74    $1.5M       Jan. 2019
                 Eden Road (US287 to Calender)