Page 358 - City of Arlington FY19 Adopted Operating Budget
P. 358

Invest in Our Economy


                                Goal 1: Enhance Economic Impact Through Development and
                            Redevelopment Efforts, Partnerships, and Investment Opportunities
                                Objective 1: Foster Development and Redevelopment in Targeted Areas
                      Project                     Performance Measure(s)             City Service Team (Department)
             IOE   Redevelopment of      Citizen satisfaction with overall quality of parks   Economic Development and
             1.1.3  Ditto Golf Course     and recreation programs and classes       Capital Investment (PWT) and
                                         Cost recovery of Golf Performance Fund    Neighborhood Services (Parks)
                                         Rounds of golf played
                                         Average rounds of golf played on playable days
             Summary:
                                                                  Milestone            Estimated      Actual
             The redevelopment of Ditto Golf Course is one of                          Completion   Completion
             many redevelopment efforts in North Arlington.
             A golf course master plan recently approved by
             City Council, will include complete renovation of   Phase 1 construction drawings   June 2016   July 2016
             the golf course, new clubhouse and maintenance   complete
             building, expanded driving range and a practice   Phase 1 project bid    Aug. 2016    Oct. 2016
             facility.  The golf course improvements will
             provide a high‐quality playing experience at an   Phase 1 construction begins   Nov. 2016   Jan. 2017
             affordable price point for Arlington residents   Phase 2 construction drawings   June 2017   June 2017
             while providing another destination for visitors   complete
             to the Entertainment District and to help support   Phase 2 project bid    July 2017   Aug. 2017
                                                         Phase 2 construction contract   Sept. 2017   Sept. 2017
             economic development
                                                         award
             Update:                                     Phase 2 construction begins   Sept. 2017   Nov. 2017
             Phase 1 (Golf Course):  Construction of the golf   Phase 3 construction drawings   Oct. 2017   Oct. 2017
             course was completed in October 2017.       complete
                                                         Phase 1 construction complete   Nov. 2017   Sept. 2018
             Phase 2 (Maintenance Package):  The west    Phase 3 project bid          Nov. 2017    Nov. 2017
             parking lot is complete. Fire lane and parking lot   Phase 3 construction contract   Dec. 2017   Dec. 2017
             striping, and the cart paths at the pump house,   award
             driving range, and east side of the Clubhouse   Phase 3 construction begins   Mar. 2018   Mar. 2018
             have been delayed due to recent rain. The cart   Phase 2 construction complete   Aug. 2018
             paths and fire lane and parking lot striping are   Golf course grand opening   Sept. 2018
             scheduled to be completed during the month of   Phase 3 construction complete   July 2019
             November. The golf course is scheduled to   Overall project completion   July 2019
                              th
             reopen November 28 .

             Phase 3 (Clubhouse Package):  This package
             includes the clubhouse; basement cart storage;
             east side of the Clubhouse parking lot, and
             fencing.  Fencing along Collins Street, Green Oaks
             Boulevard, and a substantial portion along Brown
             Boulevard is complete. Plumbing and foundation
             walls for the basement were completed in
             September. This phase is scheduled for
             completion in the fall of 2019.