Page 359 - City of Arlington FY19 Adopted Operating Budget
P. 359
Invest in Our Economy
Goal 1: Enhance Economic Impact Through Development and
Redevelopment Efforts, Partnerships, and Investment Opportunities
Objective 1: Foster Development and Redevelopment in Targeted Areas
Project Performance Measure(s) City Service Team (Department)
IOE EARL – East Arlington Recreation Citizen satisfaction with overall Economic Development and Capital
1.1.4 Center/Library Library and Parks Services Investment (PWT) and Neighborhood
Services (Library and Parks)
Summary:
Milestone Estimated Actual
Working collaboratively with other city Completion Completion
departments, as well as with architectural and Initial Project Sept. 2015 Sept. 2015
construction management professionals, to build a Schedule/Development Phase
new East Arlington Recreation Center and Library Architect/Engineer RFQ Aug. 2015 Aug. 2015
Complex. Architect/Engineer Selection Nov. 2015 June 2016
Process
Update: Design Development Mar. 2018 Mar. 2018
The current phase, Construction Documents, is Finalize construction documents Fall 2018
95% complete. Upon completion a Guaranteed Construction contract award Fall 2018
Maximum Price (GMP) will be developed and Permit Process Fall 2018
submitted for City Council approval. The GMP is on
Construction begins Fall 2018
schedule for City Council submission in January Finalize selection of furniture Fall 2019
2019.
and equipment
Recreation Center construction Fall 2019
complete
Move In – Recreation Center Spring 2020
Library construction complete Spring 2020
Move In – Library Spring 2020
28