Page 352 - City of Arlington FY19 Adopted Operating Budget
P. 352

Enhance Regional Mobility


                          Goal 2: Plan, Manage, and Maintain Public Transportation Infrastructure
                           Objective 1: Optimize Effectiveness and Efficiency of Existing Transportation System
                        Project                  Performance Measure(s)           City Service Team (Department)
             ERM    IH‐30 and SH‐360       Overall satisfaction with the      Economic Development and Capital
             2.1.2   Interchange           management of traffic flow during peak   Investment (PWT)
                                           hours
             Summary:

             The purpose of this project is to improve traffic safety   Milestone     Estimated      Actual
             and reduce traffic congestion at the interchange of                     Completion    Completion
             Interstate 30 and State Highway 360.  Formerly a toll   Package A Construction  Spring 2020
             road loop interchange, the new infrastructure will   Package B Construction  Spring 2020
             include main lane improvements and direct         Package C Construction
             connection ramps to each facility.                Package D Construction
                                                               Package E Construction  Summer 2020
             This project is split into five construction phases.
             Package A is reconstructing the Six Flags Drive Bridge
             over IH‐30 and will be bid as a joint project with the
             IH‐30/SH‐360 Interchange Project (Package B).
             Package C is the Great Southwest Industrial District
             railroad bridge crossing just south of Randol Mill Road.
             Package D includes the Randol Mill Road interchange
             improvements and Package E includes improvements
             from Abram Street to IH‐20.

             Update:
             Construction of Packages A, B, and E is proceeding
             with no significant delays or milestones achieved
                       th
             during the 4  quarter.




































                                                             21