Page 349 - City of Arlington FY19 Adopted Operating Budget
P. 349

Enhance Regional Mobility


                             Goal 1: Explore Creative, Alternative Transportation Opportunities
                                            Objective 1: Promote Regional Connectivity
                          Project                  Performance Measure(s)         City Service Team (Department)
             ERM   Autonomous Shuttle Program   Number of Events Served        Economic Development and Capital
             1.1.2                                                             Investment (CDP)
             Summary:

             The Milo project will utilize two EasyMile             Milestone      Estimated     Actual
             autonomous shuttles, named Milo, to provide                          Completion   Completion
             service along off‐street trails in the Entertainment   Report to Council   Oct. 2017   Nov. 2017
             District, connecting parking lots to AT&T Stadium   Report to Council   Jan. 2018   Feb. 2018
             and Globe Life Park. The shuttles hold twelve       Report to Council   Apr. 2018   June 2018
             passengers each and travel at a maximum speed of    Report to Council   Oct. 2017
             20 miles per hour. The City has entered into a 6‐
             month lease with a 6‐month renewal option for a
             total annual cost of $272,159.07.  Additional costs         Number of Events Served
             include branding the vehicles and other        40
             miscellaneous expenses for an anticipated total
             first‐year cost of around $300,000.            35                              37
                                                            30                           32
             Once the first year of service is underway, the City   25
             Council may elect to extend the project an     20    23 23
             additional year, offering the City more time to test   15
             the technology and gather data and input.  While                    16
                                                            10
             the project will initially provide service off‐street in         12                        12
                                                             5                                      10
             the Entertainment District, a second phase of the
             project hopes to put the driverless shuttles on‐  0
             street, possibly on and around the UT Arlington      1st Qtr    2nd Qtr     3rd Qtr    4th Qtr
             campus. Service is anticipated to run from July 2017
             through July 2018 with an additional year of service       FY 2018 Goal   FY 2018 Actual
             possible with City Council approval.  Milo will be
             operational for all major sporting and special events
             in the Entertainment District.

             Update:
             Milo service continued through August 6, 2018,
             which was the end of the one‐year pilot program.
             In the one year from August 2017 to August 2018,
             Milo service was provided at a total of 113 events,
             including events at the two stadiums, public demos,
             and special group rides. A total of 12 events were
             served during the 4  quarter FY 2018. A closeout
                             th
             report to Council is scheduled for November 2018.














                                                             18