2026 Sidewalk Projects                                                    PROJECT #                        0


         PROGRAM: STREETS PROJECT                             PROJECT MANAGER:              MATT COX



         DESCRIPTION                                             JUSTIFICATION

         1. Skyline Dr. $98,000                                  Resident safety for walking and exercising. Also
         New concrete sidewalk installation that will connect    allows for children to stay out of the street when
         2 existing sections of sidewalk on the east side of     walking to bus stop locations for school
         Skyline Dr starting at Panorama Cir to 32 Skyline
         Dr. Approximately 4,000 sq ft.
         2. Creekside Dr. $102,000
         New concrete sidewalk installation that will wrap
         around on Creekside Dr from the east side of
         Parkview at Durango, move south toward Creekside


         FUNDING TIMELINE

         2025                 2026               2027               2028              2029                2030

         BOND SERIES 2025
                  $0.00      $200,000.00               $0.00             $0.00              $0.00               $0.00



                  $0.00             $0.00              $0.00             $0.00              $0.00               $0.00



                  $0.00             $0.00              $0.00             $0.00              $0.00               $0.00
         TOTAL:

                  $0.00      $200,000.00               $0.00             $0.00              $0.00               $0.00

         PROJECT COST:
         PREVIOUS APPROVED ALLOCATION:                  $0.00

         CAPITAL REMAINING:                             $0.00
         PROJECT TOTAL                                  $0.00

         PROJECT LOCATION:
         PROJECT LOCATIO

         IMPACT ON OPERATING BUDGET:

         IMPACT ON BUDGET:                              $0.00
         IMPACT:












               FY 2024-2025                                  71                    Approved Annual Budget