Fire Station HVAC Units                                                   PROJECT #                        0


         PROGRAM: FIRE PROJECT                                PROJECT MANAGER:              JASON WISE



         DESCRIPTION                                             JUSTIFICATION

         Replacement of 2 HVAC units at Fire Station.            The Fire Station HVAC units end of life is twelve
                                                                 years. The Fire Station was built in 2012. Two unit
                                                                 systems and thermostats are required to be
                                                                 replaced in FY25.










         FUNDING TIMELINE

         2025                 2026               2027               2028              2029                2030

         MUD FUNDING
            $40,000.00              $0.00              $0.00             $0.00              $0.00               $0.00



                 $0.00              $0.00              $0.00             $0.00              $0.00               $0.00



                 $0.00              $0.00              $0.00             $0.00              $0.00               $0.00
         TOTAL:

            $40,000.00              $0.00              $0.00             $0.00              $0.00               $0.00

         PROJECT COST:
         PREVIOUS APPROVED ALLOCATION:                  $0.00

         CAPITAL REMAINING:                        $40,000.00
         PROJECT TOTAL                             $40,000.00

         PROJECT LOCATION:
         PROJECT LOCATIO                        FIRE STATION

         IMPACT ON OPERATING BUDGET:

         IMPACT ON BUDGET:                              $0.00
         IMPACT: