Wilshire Stormwater/Drainage Project PROJECT # 0
PROGRAM: STORM DRAINAGE FUND PROJECT MANAGER: MATT COX
PROJECT
DESCRIPTION JUSTIFICATION
Wilshire Stormwater and Drainage Improvement Engineering reports and studies show current
Project- $1,500,000.00 existing stormwater infrastucture to be undersized
and inadequate during heavy rainfall affecting 4
residential properties between Wilshire Dr and
Trophy Club Dr. Mulitple floodings have occurred
inside of homes on Wilshire Dr resulting in private
property damage.
FUNDING TIMELINE
2025 2026 2027 2028 2029 2030
STORM DRAINAGE UTILITY
$1,500,000.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL:
$1,500,000.00 $0.00 $0.00 $0.00 $0.00
PROJECT COST:
PREVIOUS APPROVED ALLOCATION: $0.00
CAPITAL REMAINING: $1,500,000.00
PROJECT TOTAL $0.00
PROJECT LOCATION:
PROJECT LOCATIO Wilshire
IMPACT ON OPERATING BUDGET:
IMPACT ON BUDGET: $0.00
IMPACT:
FY 2024-2025 68 Approved Annual Budget