Page 81 - CityofTrophyClubFY25AdoptedBudget
P. 81
Fire Department Paint Project PROJECT # 0
PROGRAM: FIRE PROJECT PROJECT MANAGER: JASON WISE
DESCRIPTION JUSTIFICATION
Update paint colors and repair sheet rock on the The fire station was built in 2011. Paint is faded
interior and apparatus bay. and sheet rock is damaged from roof leaks.
FUNDING TIMELINE
2025 2026 2027 2028 2029 2030
MUD FUNDING
$0.00 $35,000.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL:
$0.00 $35,000.00 $0.00 $0.00 $0.00 $0.00
PROJECT COST:
PREVIOUS APPROVED ALLOCATION: $0.00
CAPITAL REMAINING: $35,000.00
PROJECT TOTAL $35,000.00
PROJECT LOCATION:
PROJECT LOCATIO FIRE STATION
IMPACT ON OPERATING BUDGET:
IMPACT ON BUDGET: $0.00
IMPACT:
FY 2024-2025 73 Approved Annual Budget