Page 83 - CityofTrophyClubFY25AdoptedBudget
P. 83

Street Lights at Bobcat and Parkview                                      PROJECT #


         PROGRAM: STREETS PROJECT                             PROJECT MANAGER:              MATT COX



         DESCRIPTION                                             JUSTIFICATION

         Upgrade street lighting on Bobcat Blvd. and             The existing lighting on Bobcat and appoximately
         Parkview Dr. to meet Town's minimum standards           1,500 ft on Parkview do not meet the Town's
         on distances between light poles. Proposal will         minimum standards on distances between light
         include an additional 29 decorative light poles on      poles. The inadequate lighting presents safety
         Bobcat and Parkview. Waiting on final proposal          concerns at night for pedestrians and drivers.
         from Oncor.








         FUNDING TIMELINE

         2025                 2026               2027               2028              2029                2030

         BOND SERIES 2025
                  $0.00      $200,000.00               $0.00             $0.00              $0.00               $0.00



                  $0.00             $0.00              $0.00             $0.00              $0.00               $0.00



                  $0.00             $0.00              $0.00             $0.00              $0.00               $0.00
         TOTAL:

                  $0.00      $200,000.00               $0.00             $0.00              $0.00               $0.00

         PROJECT COST:
         PREVIOUS APPROVED ALLOCATION:            $200,000.00

         CAPITAL REMAINING:                             $0.00
         PROJECT TOTAL                            $200,000.00

         PROJECT LOCATION:
         PROJECT LOCATIO                   Bobcat and Parkview

         IMPACT ON OPERATING BUDGET:

         IMPACT ON BUDGET:                              $0.00
         IMPACT:












               FY 2024-2025                                  75                    Approved Annual Budget
   78   79   80   81   82   83   84   85   86   87   88