Page 458 - FY 2025 Adopted Operating Budget and Business Plan
P. 458

Return to Table of Contents




                                        Culture/Recreation/Education

               Goal 1: Provide Activities, Educational Opportunities, and Services that Meet the Needs of the
                                                        Community
                         Objective 1: Develop and Implement Programming Based on the Needs of the Community
                       Project                      Performance Measure(s)                   Department(s)
             Core  ACTIV – Active Adult   • Overall Satisfaction of Project Management  Asset Management and
             CRE   Center Construction    • Project Completion on Time and at Budget  Parks & Recreation
             1.1.1                        • Citizen Satisfaction with Overall Quality of Parks
                                            and Recreation Programs and Classes
             Summary:
                                                                                         Estimated     Actual
                                                                       Milestone
             In a special election on May 6, 2017, Arlington voters                     Completion   Completion
             approved obligation bonds to build an Active Adult Center.   Initial Project   Jan. 2019   Jan. 2019
             This new facility for residents 50 years of age and older will   Schedule/Development
             be located on the southwest corner of the Pierce Burch   Phase
             Water Treatment site on Green Oaks Boulevard between   Architect/Engineer RFQ   July 2019   July 2019
             W. Arkansas Lane and W. Pioneer Parkway.           Architect/Engineer      Oct. 2019    Dec. 2019
                                                                Selection Process
             Update:                                            Council Approval of     Dec. 2019    Mar. 2020
                   th
             In the 4  Quarter of FY 2024, all three buildings have been   Architect Contract
             weathered in. Windows and roofs are complete. Exterior   CMAR Delivery Method   Fall 2019   Jan. 2020
             masonry veneer, wood and metal paneling are 80%    Council Approval
             complete. Overall project completion is 79%.       Finalize Construction   Fall 2022    Fall 2022
                                                                Documents
                                                                Permit Process          Fall 2022    Fall 2022
                                                                Guaranteed Maximum      Fall 2022    Fall 2022
                                                                Price to Council
                                                                Construction Begins     Winter 2022   Jan. 2023
                                                                Finalize Selection of   Fall 2023    June 2023
                                                                Furniture and Equipment
                                                                Construction Complete   Winter 2024




































                                                             85