Page 99 - ArlingtonFY24AdoptedBudget
P. 99

Business Plan




                                                    Infrastructure


                                      Goal 1: Plan, Manage, and Maintain Public Assets
                                    Objective 2: Maintain City Standards for all Municipal Buildings
                          Project                       Performance Measure(s)                Department(s)
             Core  Police Evidence Storage, Crime   • Overall Satisfaction of Project Management   Asset Management and
             INF   Lab & North District Substation    • Project Completion on Time and at Budget    Police
             1.2.1
             Summary:
                                                                   Milestone           Estimated     Actual
             In November 2018, Arlington voters approved                              Completion   Completion
             general obligation bonds to design and build a new   Initial Project     May 2021     Jan. 2022
             Police Evidence Storage Facility. In Winter of 2021,   Schedule/Development Phase
             City Council approved the purchase of a commercial   Request for Qualifications for  June 2021   Feb. 2022
             property at 1715 E. Lamar Blvd. This property will be   Architect/Engineer
             converted into a new facility for the Police   Architect/Engineer Selection   Spring 2022   June 2022
             Department that will house a North District    Process
             substation, evidence storage and crime lab.    Council Approval of Architect  Spring 2022   June 2022
                                                            Contract
                                                            Design Phase              Summer 2023
                                                            Finalize Construction     Fall 2023
                                                            Documents
                                                            Permit Phase              Winter 2023

                                                            Bidding Phase             Spring 2024
                                                            Construction Begins       Summer 2024
                                                            Finalize Selection of Fixtures,   Fall 2024
                                                            Furniture, and Equipment
                                                            Construction Complete     Fall 2025


                                                    Infrastructure


                                      Goal 1: Plan, Manage, and Maintain Public Assets
                                    Objective 2: Maintain City Standards for all Municipal Buildings
                      Project                   Performance Measure(s)                   Department(s)
             Core  Fire Station #8      • Overall Satisfaction of Project Management  Asset Management and Fire
             INF   Rebuild              • Project Completion on Time and at Budget
             1.2.2
             Summary:
                                                                     Milestone           Estimated     Actual
             In November 2018, Arlington voters approved general                        Completion   Completion
             obligation bonds for the reconstruction of Fire Station   Issue a RFQ for Architects   Spring 2022   Spring 2022
             #8. The Arlington Fire Department has partnered   Select an Architect for Design  Summer 2022  Fall 2022
             with Asset Management to re-design the existing   Council Approval of Architect  Fall 2022   Fall 2022
             facility located at 2004 Madison Drive. The station is at   Contract
             the north part of the City and built in 1978 and is   Design Phase        Summer 2023
             currently managed by the Fire Department and was   Permit Phase           Summer 2023
             most recently remodeled in 2018.                Bidding Phase             Fall 2023
                                                             Permit Phase              Summer 2023
                                                             Construction Phase        Summer 2024

                                                               Move In                 Summer 2024