Business Plan
Infrastructure
Goal 1: Plan, Manage, and Maintain Public Assets
Objective 2: Maintain City Standards for all Municipal Buildings
Project Performance Measure(s) Department(s)
Core City Tower Improvements • Overall Satisfaction of Project Management Asset Management
INF • Project Completion on Time and at Budget
1.2.3
Summary:
Milestone Estimated Actual
Phase 1 of the City Tower Improvements includes: Completion Completion
structural improvements throughout the entire Phase 1:
building; replacement of aging HVAC Select Structural Engineer Spring 2022 Spring 2022
infrastructure; and parking lot lighting and security. Initial Project Summer 2022 Summer 2022
Schedule/Development Phase
Phase 2 of the City Tower Improvements includes: Council Approval of Architect Fall 2022 Fall 2022
roof replacement; and general facility condition Contract
improvements throughout the building. Construction Documents Winter 2022 Winter 2022
Permitting Winter 2022 Winter 2022
Phase 3 of the City Tower Improvements includes Construction Start Fall 2023
elevator system replacement. Construction Completion Fall 2024
Project Completion Fall 2024
Phase 2:
Select Architect Spring 2023
Initial Project Spring 2023
Schedule/Development Phase
Council Approval of Architect Summer 2023
Contract
Construction Documents Winter 2023
Permitting Winter 2023
Construction Start Spring 2024
Construction Completion Fall 2024
Project Completion Fall 2024
Phase 3:
Select Design-Build Firm for Summer 2023
Elevators Replacement
Initial Project Summer 2023
Schedule/Development Phase
Council Approval of Architect Fall 2023
Contract
Construction Documents Winter 2023
Permitting Winter 2023
Construction Start Spring 2024
Construction Completion Fall 2024
Project Completion Fall 2024