CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                   PARKS


                         Funding   Total Prior                                               Beyond /
          Project number                     FY 2023   FY 2024  FY 2025   FY 2026   FY 2027              Total
                          Source   Funding                                                   Unfunded
          Carillon Parks
          (Corporate Park,
          Lake Park, The   Funding is planned for improvements at Carillon parks as per the adopted Southlake 2035 Parks, Recreation & Open Space
                        Master Plan.  Project scope includes: trail signage, lighting and distance markers, park signage, water bottle refill stations,
          Preserve Park,
          Villa Park North &  tree planting/irrigation, and park amenities.
          Villa Park South)
          2022-71       SPDC              $0       $0        $0       $0        $0        $0   $525,000   $525,000



                        Funding is planned for improvements at Noble Oaks Park as per the adopted Southlake 2035 Parks, Recreation & Open
          Noble Oaks Park   Space Master Plan.  The project scope includes: park and educational signage, additional park amenities and water bottle
          Improvements
                        refill station.
          2022-72       SPDC              $0       $0        $0       $0        $0        $0   $100,000   $100,000



          Oak Pointe Park   Funding is planned for the design and development of improvements at Oak Pointe Park as per the adopted Southlake
                        2035 Parks, Recreation & Open Space Master Plan.  The project scope includes: trail expansion and connectivity and park
          Improvements
                        amenities.
          2022-73       SPDC              $0       $0        $0       $0        $0        $0   $110,000   $110,000

                        Funding is planned for the design and development of improvements at The Cliffs Park as per the adopted Southlake 2035
          The Cliffs Park   Parks, Recreation & Open Space Master Plan.  The project scope includes: trail connectivity and distance markers, off street
          Improvements  parking, pedestrian crossing at White Chapel Blvd., water bottle refill station, tree planting, irrigation, gazebo, trail lighting,
                        playground, park signage and park amenities.
          2022-74       SPDC              $0       $0        $0       $0        $0        $0  $1,260,000  $1,260,000


        Parks Total               $15,249,134  $6,770,000  $6,750,000 $21,800,000  $4,000,000  $4,000,000 $43,615,000 $102,184,134