Page 346 - Southlake FY23 Budget
P. 346

CAPITAL IMPROVEMENTS  PROGRAM (CIP)
                                                                                 Water
                                                                                 WATER


                             Funding   Total Prior                                               Beyond /
              Project number                     FY 2023  FY 2024   FY 2025   FY 2026  FY 2027               Total
                             Source    Funding                                                   Unfunded
              Site
              Improvements
              at Public Works   Identified under the The American Water Infrastructure Act (AWIA) Risk and Resiliency Assessment, this project will provide
              Facilities (AWIA/  site improvements to mitigate risk and resiliency of Public Works facilities.
              SB3 Project)


              2023-11       Utility Fund     $0        $0   $70,000       $0        $0       $0         $0    $70,000



              Constituent
              Tracer Study   Identified under the The American Water Infrastructure Act (AWIA) Risk and Resiliency Assessment, this project will model
                            how quickly water quality can be impacted from the ground and elevated storage tanks within the water distribution system
              (AWIA/SB3     under various operating scenarios.
              Project)
              2023-12       Utility Fund     $0        $0       $0   $100,000       $0       $0         $0   $100,000


              New Grapevine
              Emergency
              Interconnect   Identified under the The American Water Infrastructure Act (AWIA) Risk and Resiliency Assessment, this project will provide
              (AWIA/SB3     an additional emergency interconnect with the City of Grapevine to mitigate water supply under emergency operations.
              Project)

              2023-13       Utility Fund     $0        $0       $0   $100,000  $450,000      $0         $0   $550,000


              8-inch Water line
              along E. Bob   Funding is planned for right-of-way, engineering design and construction of an 8-inch water line to connect the dead-end
              Jones Road to   water lines located at Walnut Brooks Court and East Bob Jones Road. This project will create a looped water system,
              Walnut Brooks   improving water quality and fire protection within this region.
              Court
              2022-34c      Utility Fund     $0        $0   $70,000  $300,000  $1,200,000    $0         $0  $1,570,000

                            Water
              2022-34c                       $0        $0  $180,000       $0        $0       $0         $0   $180,000
                            Impact Fee
                            Total            $0        $0  $250,000  $300,000  $1,200,000    $0         $0  $1,750,000




              12-inch Water
              line along Shady   Funding is planned for right-of-way, engineering design, and construction of a 12-inch water line along Shady Oaks Drive
              Oaks Drive from   from Fox Glen to West Dove Road and an 8-inch sewer line on Shady Oaks Drive from Highland Street to Fox Glen. This
              Highland to West
              Dove Road and   project follows the 12-inch water line project paralleling Shady Oaks from Highland Street to Fox Glen (Phase I). Phase II is
                            the continuation to the north from Fox Glen to West Dove Road.
              8-inch Sewer
              (Phase II)


              2022-32c      Utility Fund     $0        $0  $400,000       $0  $4,600,000     $0         $0  $5,000,000
                            Water
              2022-32c                       $0        $0  $250,000  $450,000   $40,000      $0         $0   $740,000
                            Impact Fee
                            General
              2022-32c                       $0        $0  $120,000       $0   $600,000      $0         $0   $720,000
                            Fund
                            Total            $0        $0  $770,000  $450,000  $5,240,000    $0         $0  $6,460,000