CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                   WATER


                         Funding   Total Prior                                               Beyond /
          Project number                     FY 2023   FY 2024  FY 2025   FY 2026   FY 2027              Total
                          Source   Funding                                                   Unfunded

          12-inch Water
          Line along Union  Funding is planned for engineering design, right-of-way, and construction of a 12-inch water line along Union Church and
          Church/ Pearson
          from FM 1938 to   Pearson Lane from FM 1938 to FM 1709. This project includes approximately 3,220 linear feet of new sidewalk.
          FM 1709



          2022-31c      Water        $700,000      $0        $0       $0        $0        $0        $0    $700,000
                        Impact Fee
          2022-31c      Utility Fund  $700,000  $385,000     $0       $0        $0        $0        $0  $1,085,000
                        Total      $1,400,000  $385,000      $0       $0        $0        $0        $0  $1,785,000



          12-inch Water
          Line along E.   Funding is planned for engineering design, right-of-way, and construction of a 12-inch water line along E. Dove from Estes
          Dove from Estes   Park to Winfield Court.  This project includes approximately 980 linear feet of new sidewalk.
          Park to Winfield
          Estates


          2023-09c      Water        $500,000      $0        $0       $0        $0        $0        $0    $500,000
                        Impact Fee
          2023-09c      Utility Fund  $50,000  $105,000      $0       $0        $0        $0        $0    $155,000

                        Total        $550,000  $105,000      $0       $0        $0        $0        $0    $655,000



          Shady Oaks 12-  Funding is requested for the construction and right-of-way acquisition of a 12-inch water line along Shady Oaks Drive from
                        Highland Street to West Dove Road and Phase II of this project will include an 8-inch sewer line along Shady Oaks Drive
          inch Water Lines   from Highland Street to Fox Glen. This project received prior funding from the FY 2009 sewer impact fees and FY 2017
          (Phase I)
                        Utility Fund.
          2022-26c      Utility Fund  $1,787,000  $210,000   $0       $0        $0        $0        $0  $1,997,000



          Matching Funds


          System Capacity
          Improvements   Funding provides resources to reimburse developers for the oversizing of water lines to meet the requirements of the
                        Southlake 2030 Water Master Plan in cases where the developer is not required to provide the ultimate size of the line to
          (Water) - Future   serve proposed developments.
          Projects

                        Water
          2022-30                    $880,000  $180,000  $115,000  $122,000  $128,000  $135,000  $142,000  $1,702,000
                        Impact Fee


          Future Projects
          Pearson Pump
          Station Risk
          and Resiliency   Identified under the The American Water Infrastructure Act (AWIA) Risk and Resiliency Assessment, this project will provide
                        site improvements to mitigate risk and resiliency of Public Works facilities including a fire suppression system for the control
          Improvements
          (AWIA/SB3     room and a masonry enclosure with bridge crane or roof hatches around the weather-exposed pumps.
          Project)
          2023-10       Utility Fund     $0        $0   $288,750  $2,205,000    $0        $0        $0  $2,493,750