CITY OF HALTOM CITY ANNUAL BUDGET, FY2023                     General Fund





                                                                  Actual     Adopted      Projected     Adopted
           EXPENDITURES                                          FY 2021     FY 2022       FY 2022      FY 2023
           Personnel                                             $548,205      $858,730      $858,730    $852,325
           Operations                                             520,392       505,550       440,735     521,100
           Capital                                                      0        60,000        60,000     635,000
           Total                                                $1,068,597   $1,424,280    $1,359,465   $2,008,425


                                                                  Actual     Adopted      Projected     Adopted
           STAFFING                                 Class Range  FY 2021     FY 2022       FY 2022      FY 2023
           Street Maintenance Supervisor            2901   63      0.5         0.5           0.5          0.5
           Public Works Crewleader                  2905   49       2           2             2            2
           Senior Equipment Operator                2906   44       2           2             2            2
           Sign Specialist                          2909   44       1           1             1            1
           Equipment Operator                       2910   41       3           3             3            3
           Public Works Maintenance Worker          2911   37       3           3             3            3
           Sign Technician                          2913   41       0           1             1            1
           Total                                                  11.5         12.5         12.5         12.5




                                                                        Actual     Actual     Actual     Target
                                        PERFORMANCE MEASURES
                                                                       FY2020     FY2021     FY2022      FY2023
                                    Tons of asphalt utilized in patching projects  2,412  1,591  1,300    1,700
                                    Tons of cold mix used in pothole patching  19    18        14          20
                                    Traffic signal repair work orders completed   277  298     431        350
                                    Regulatory Signs replaced            107        211        218        200
            Goal 6:  Address Critical Facility
               & Infrastructure Needs  Miles of lane crack-sealed        4.04       0.50       0.50       0.50
                                    Miles of lane over-layed with asphalt  1.14     0.23       0.15       0.75
                                    Miles of lane replaced at full-depth with asphalt  0.30  0.56  0.00   0.50
                                    Miles of streets swept               2,794      1,813     2,405       2,450
                                    Feet of concrete curb replaced       1,903      1,811      367        1,700






                         Tons of Asphalts Utilized                          Sign Replaced and Streets Swept
            3,000                                                        2,794
                                                                  200                                        3,000
            2,500                                                                           2,405    2,450
                                                                                                             2,500
            2,000                                                 150             1,813                      2,000
            1,500                                                 100                                        1,500
            1,000                                                  50                                        1,000
             500                                                          107      211      218       200    500
                     2,412      1,591      1,300      1,700         0                                        0
              0                                                          2020      2021     2022     2023
                     2020       2021       2022        2023                      Regulatory Signs Replaced
                            Asphalt Patching Projects                            Miles of Streets Swept
   81   82   83   84   85   86   87   88   89   90   91