CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                                                               WATEr



                                   City of Southlake FY 2022 CIP Project Status Form

                   12-inch Water line along North Peytonville from Concho Court to Southridge Lakes Parkway

              DEPARTMENT: Public Works
              PROJECT
              LOCATION:   North Peytonville from Concho Court to Southridge Lakes Parkway

              PROJECT TIMELINE: Oct 2023  to  Sept 2026
              DESCRIPTION:
               Funding is planned for right-of-way, engineering design and construction of a 12-inch
               water line along North Peytonville from Concho Court to Southridge Lakes Parkway to
               increase capacity in this region and to compensate for development and growth.








                                                                       New Request   Continuation Project  Partnership
               JUSTIFICATION:                                          Mandated /    Replacement / Major   Community
                                                                        Public Health /   Rehab or Protection      Need / Service
               Up-sizing this line will increase available pressure/flow in the area improving fire flow  Safety  of Capital Stock  Enhancement
               capability, increasing level of service and public safety for existing and future
               development.                                             2030/2035 COMPREHENSIVE PLAN? If yes, include ref:
                                                                        Water System Master Plan #19 -WWS9-Tier 2
               ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
               Service ability will continue at its current level with limited pressure/flow.
                                                                        REVENUE GENERATING? If yes, please explain:
               STRATEGIC FOCUS AREA: Infrastructure
               PROJECT #:  2022-36
                                                        EXPENDITURE SCHEDULE
                CAPITAL PROJECT COSTS  TOTAL PRIOR  2022  2023    2024     2025      2026    UNFUNDED    TOTAL
                  PLANNING / FEASIBILITY STUDY                                                             0
                ENGINEERING & DESIGN; TESTING                             65,000    50,000               115,000
                    LAND & ROW ACQUISITION                                          50,000               50,000
               LANDSCAPING,  ART,  URBAN  DESIGN                                                           0
                          CONSTRUCTION                                             450,000               450,000
                          CONTINGENCY                                                                      0
                              TOTAL    0         0        0        0      65,000   550,000      0        615,000
                                                         OPERATIONAL IMPACT
               OPERATIONAL PROJECT COSTS  TOTAL PRIOR  2022  2023  2024    2025      2026    UNFUNDED    TOTAL
                       MAINTENANCE COSTS                                            10,000    10,000     20,000
                        PERSONNEL COSTS                                                                    0
                              TOTAL    0         0        0        0        0       10,000    10,000     20,000
                                                          FUNDING SCHEDULE
                 CAPITAL FUNDING SOURCE  TOTAL PRIOR  2022  2023  2024     2025      2026    UNFUNDED    TOTAL
                          GENERAL FUND                                                                     0
                               CEDC                                                                        0
                               CCPD                                                                        0
                   PARK DEDICATION FEE FUND                                                                0
                         PUBLIC ART FUND                                                                   0
                   ROADWAY IMPACT FEE FUND                                                                 0
                  SANITARY SEWER IMPACT FEE                                                                0
                               SPDC                                                                        0
               STORMWATER UTILITY SYSTEM FUND                                                              0
                              TIRZ #1                                                                      0
                           UTILITY FUND                                   65,000   550,000               615,000
                    WATER IMPACT FEE FUND                                                                  0
                              TOTAL    0         0        0        0      65,000   550,000      0        615,000
               CCPD: CRIME CONTROL & PREVENTION DISTRICT                                SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
                CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                      TIRZ #1:  TAX INCREMENT REINVESTMENT ZONE #1
                                                                           BUDGET BOOK   |  FY 2022 City of Southlake  431
                                                                                         WWW.CITYOFSOUTHLAKE.COM
   427   428   429   430   431   432   433   434   435   436   437