CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                                                               WATEr



                                   City of Southlake FY 2022 CIP Project Status Form

                               12-inch Water line along East Continental Boulevard to Breeze Way

               DEPARTMENT: Public Works
               PROJECT
               LOCATION:  East Continental Boulevard to Breeze Way

               PROJECT TIMELINE: Oct 2023  to  Sept 2025
               DESCRIPTION:
               Funding is planned for right of way, engineering design, and construction of a 12-inch
               water line along East Continental Boulevard to Breeze Way.









                                                                       New Request   Continuation Project  Partnership
               JUSTIFICATION:                                          Mandated /    Replacement / Major   Community
               Up-sizing this line will increase available pressure/flow in the area improving fire flow  Public Health /   Rehab or Protection   Need / Service
                                                                       Safety
                                                                                     of Capital Stock
                                                                                                       Enhancement
               capability, increasing level of service and public safety for existing and future
               development.                                            2030/2035 COMPREHENSIVE PLAN? If yes, include ref:

                                                                        Water System  Master Plan #21-WWS9 -Tier 2
               ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
               Service ability will continue at its current level with limited pressure/flow.
                                                                        REVENUE GENERATING? If yes, please explain:
               STRATEGIC FOCUS AREA: Infrastructure
               PROJECT #:  2022-38
                                                        EXPENDITURE SCHEDULE
                CAPITAL PROJECT COSTS  TOTAL PRIOR  2022  2023     2024    2025      2026    UNFUNDED    TOTAL
                  PLANNING / FEASIBILITY STUDY                                                             0
                 ENGINEERING & DESIGN; TESTING                            100,000   50,000               150,000
                     LAND & ROW ACQUISITION                                         50,000               50,000
               LANDSCAPING,  ART,  URBAN  DESIGN                                                           0
                          CONSTRUCTION                                             700,000               700,000
                          CONTINGENCY                                                                      0
                              TOTAL    0         0        0        0      100,000  800,000      0        900,000
                                                         OPERATIONAL IMPACT
               OPERATIONAL PROJECT COSTS  TOTAL PRIOR  2022  2023  2024    2025      2026    UNFUNDED    TOTAL
                       MAINTENANCE COSTS                                                                   0
                        PERSONNEL COSTS                                                                    0
                              TOTAL    0         0        0        0        0         0         0          0
                                                          FUNDING SCHEDULE
                 CAPITAL FUNDING SOURCE  TOTAL PRIOR  2022  2023   2024    2025      2026    UNFUNDED    TOTAL
                          GENERAL FUND                                                                     0
                               CEDC                                                                        0
                               CCPD                                                                        0
                   PARK DEDICATION FEE FUND                                                                0
                         PUBLIC ART FUND                                                                   0
                   ROADWAY IMPACT FEE FUND                                                                 0
                  SANITARY SEWER IMPACT FEE                                                                0
                               SPDC                                                                        0
               STORMWATER UTILITY SYSTEM FUND                                                              0
                              TIRZ #1                                                                      0
                           UTILITY FUND                                   100,000  800,000               900,000
                     WATER IMPACT FEE FUND                                                                 0
                              TOTAL    0         0        0        0      100,000  800,000      0        900,000
               CCPD: CRIME CONTROL & PREVENTION DISTRICT                                SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
                CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                      TIRZ #1:  TAX INCREMENT REINVESTMENT ZONE #1
                                                                           BUDGET BOOK   |  FY 2022 City of Southlake  433
                                                                                         WWW.CITYOFSOUTHLAKE.COM
   429   430   431   432   433   434   435   436   437   438   439