Page 304 - Project Detail Sheet_AdoptedBook
P. 304
ADOPTED | BUDGET
Utility Capital Projects
Conn Pump Station and Electrical Rehabilitation
UT2008
352-(&7 '(6&5,37,21 -867,),&$7,21
The Conn Pump Station provides potable water from the south of the city to just south of Mid-Cities Blvd through four pumps
located on the site. Three of these pumps were replaced 6 years ago. Staff became aware of noticeable wear and tear on the
pumps through inspections and failures. Freese and Nichols Engineering group was hired to conduct a piping analysis to
determine the cause for the premature pump issues. Through this analysis, Freese and Nichols was able to determine that the
pump issues were caused by the net positive suction head created by the piping alignment on the suction side of the pumps.
The suction piping has a 90 degree bend located too close to the pump on three of the four pumps. The analysis also shows
that the electrical panels will have to be moved to correct the alignment of the piping and to meet clearance requirements from
the National Electric Code.
Funding Source: Certificates of Obligation.
352-(&7 67$786 25,*,1$/ 25,*,1$/
67$57 '$7( 5(9,6,21 (1' '$7( 5(9,6,21
Professional Services
Engineering 10/2019 09/2020 06/2021
Land/ROW Acquisition
Construction 02/2020 08/2021 09/2020 08/2022
Other
5(9,6,21 (;3/$1$7,21
The pump station design recommendation for variable speed pumps increased the base project cost, and an increase in
construction prices overall caused the construction bids to exceed the project estimate. Surplus funds from UT1607 are
proposed to offset the deficit and to provide for a project contingency.
),1$1&,$/ '$7$
$'237(' 5(9,6(' 727$/
%8'*(7 7+58 352-(&7 %8'*(7 7+58 5(0$,1,1* 352-(&7
5(9,6,21 %$/$1&( &267
)81',1* 6285&(6
Certificates of Obligation $1,500,000 $0 $1,500,000 $1,500,000
Project Savings (UT1607) 1,100,000 1,100,000 $1,100,000
0 $0
0 $0
0 $0
7RWDO $1,500,000 $1,100,000 $2,600,000 $0 $2,600,000
352-(&7 (;3(1',785(6
$0 $0
Professional Services
Engineering/Design 328,975 25 329,000 $329,000
Land/ROW Acquistion 0 0 $0
Construction 1,171,025 1,099,975 2,271,000 $2,271,000
Other 0 $0
7RWDO $1,500,000 $1,100,000 $2,600,000 $0 $2,600,000
,03$&7 21 23(5$7,1* %8'*(7
$118$/ 23(5$7,1* ,03$&7 727$/
Projected $0
291
NRH | TEXAS