Page 275 - Project Detail Sheet_AdoptedBook
P. 275

ADOPTED | BUDGET

                                         Major Capital Equipment Capital Projects
                Department                                     Project Title                         Project Number
        Fleet Services                               Backhoe Replacement (Unit 5526)                      FS2202
                                                      Project Description
        This is for the purchase of a new backhoe to replace unit 5526, a 2006 year-model New Holland utilized by the Public Works
        Department.









                                                      Project Justification
        The CIP Major Capital equipment replacement program was implemented using the recommendations obtained in an independent
        study conducted for the City by Peat Marwick in August of 1986 and August of 1993 which recommended a minimum 10-year
        replacement for capital equipment.  At the 10-year interval, the equipment is evaluated for replacement based on frequency of use,
        the number of like equipment in the fleet, equipment condition, and the availability of parts and service.

        Funding Source: Fleet Fund Reserves (520).












        Project Schedule            Beginning Date   Ending Date        History          Fiscal Year   Amount
        Professional Services                                        Proposed              2021-22       $135,000
        Engineering/Design               10/2021         11/2021         Total                           $135,000
        Land/ROW Acquisition
        Construction                     11/2021         05/2022
        Other
        Total Schedule                   10/2021         05/2022
        Sources of Funds             Appr. To Date  2021‐22 Budget  2022‐23 Estimate  2023‐Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves                              0          135,000               0               0         $135,000
        Sales Tax
        Other
        Total Funding                        $0         $135,000              $0              $0          $135,000

        Project Costs                  To Date    2021‐22 Budget  2022‐23 Estimate   2023‐Completion    Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                          0           135,000              0               0          $135,000
        Other
        Total Costs                          $0          $135,000             $0              $0          $135,000
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2020‐21       2021‐22      2022‐23       2023‐24       2024‐25     Total Impact
        Amount                           $0            $0            $0            $0            $0           $0