Invest in Our Economy
Goal 1: Enhance Economic Impact Through Development and
Redevelopment Efforts, Partnerships, and Investment Opportunities
Objective 1: Foster Development and Redevelopment in Targeted Areas
Project Performance Measure(s) City Service Team (Department)
IOE South SH‐360 Corridor Completion of Plan Shared Services (Office of Strategic
1.1.5 Development Strategy Initiatives)
Summary:
Milestone Estimated Actual
The South SH360 Corridor Development Strategy will Completion Completion
establish a vision for SH360 from I‐20 to the southern City Issue Request for Jan. 2021 Jan. 2021
Limit. The terminal build‐out of SH360 is an eight‐lane Qualifications
divided highway, and this plan will develop a vision with the Select and Contract with Apr. 2021 Mar. 2021
community for the optimal use of remaining development Consultant
opportunities along the corridor, while protecting Draft Plan Jan. 2022
established residential areas. Final Plan Mar. 2022
Update:
th
In the 4 quarter, we hosted a public meeting and an online
survey, which received 286 responses, and a second
Advisory Committee meeting on August 11, 2021. The
project is on track to be complete in early 2022.
More information about this project is available at
www.arlingtontx.gov/360strategy.