                                              Invest in Our Economy


                                Goal 1: Enhance Economic Impact Through Development and
                            Redevelopment Efforts, Partnerships, and Investment Opportunities
                                Objective 1: Foster Development and Redevelopment in Targeted Areas
                     Project                    Performance Measure(s)             City Service Team (Department)
             IOE   Redevelopment of     Overall Satisfaction of Project Management   Shared Services (AM) and
             1.1.1  Texas Rangers Golf    Project Completion on Time and at Budget   Neighborhood Services (Parks)
                   Course              Citizen Satisfaction with Overall Quality of Parks
                                        and Recreation Programs and Classes
             Summary:
                                                                    Milestone          Estimated     Actual
             The redevelopment of Texas Rangers Golf Course is                        Completion   Completion
             one of many redevelopment efforts in North       Phase 1 construction   June 2016     July 2016
             Arlington. The golf course master plan approved by   drawings complete
             City Council includes a complete renovation of the   Phase 1 project bid   Aug. 2016   Oct. 2016
             golf course, new clubhouse and maintenance       Phase 1 construction   Nov. 2016     Jan. 2017
             building, expanded driving range and a practice   begins
             facility.  The golf course improvements will provide a   Phase 2 construction   June 2017   June 2017
             high‐quality playing experience at an affordable price   drawings complete
             point for Arlington residents while providing another
                                                              Phase 2 project bid    July 2017     Aug. 2017
             destination for visitors to the Entertainment District.    Phase 2 construction   Sept. 2017   Sept. 2017
                                                              contract award
             The project is constructed in the following phases:   Phase 2 construction   Sept. 2017   Nov. 2017
             Phase 1 – Golf Course construction               begins
             Phase 2 – Maintenance, on‐course restrooms;      Phase 3 construction   Oct. 2017     Oct. 2017
             temporary clubhouse and parking lot              drawings complete
             Phase 3 – Clubhouse
                                                              Phase 1 construction   Nov. 2017     Oct. 2017

             Phase 3, the Clubhouse, is the only phase remaining   complete
                                                              Phase 3 project bid    Nov. 2017     Nov. 2017
             to complete. The estimated completion timeframe
                                                              Phase 3 construction   Dec. 2017     Dec. 2017
             for this phase was revised from July 2019 to
                                                              contract award
             December 2019 due to rebidding the construction
             contract to keep the cost within budget.  The    Phase 3 construction   Mar. 2018     Mar. 2018
             completion date was extended until November 2020.     begins
                                                              Phase 2 construction   Aug. 2018     Apr. 2019
                                                              complete
             Update:
                   th
             In the 4  quarter of FY 2021, the contractor     Golf course grand      Sept. 2018    May 2019
             completed warranty items. Retainage will be      opening
             released by the end of October 2021.             Phase 3 construction   Feb. 2021     Feb. 2021
                                                              complete
                                                              Overall project        Feb. 2021     Apr. 2021
                                                              completion