                                              Invest in Our Economy


                                Goal 1: Enhance Economic Impact Through Development and
                            Redevelopment Efforts, Partnerships, and Investment Opportunities
                                Objective 1: Foster Development and Redevelopment in Targeted Areas
                         Project                         Performance Measure(s)               City Service Team
                                                                                                (Department)
             IOE     East Arlington Recreation     Overall Satisfaction of Project Management   Shared Services (AM) and
             1.1.2   Center/Library            Project Completion on Time and at Budget   Neighborhood Services
                                               Citizen Satisfaction with Overall Library and Parks   (Library and Parks)
                                                Services
             Summary:
                                                                           Milestone      Estimated    Actual
             Working collaboratively with other city departments, as well as              Completio  Completio
             with architectural and construction management professionals,                    n          n
             to build a new East Arlington Recreation Center and Library   Initial Project   Sept. 2015   Sept. 2015
             Complex.                                                 Schedule/Developme
                                                                      nt Phase
             Update:                                                  Architect/Engineer   Aug. 2015   Aug. 2015
             The grand opening celebration for the 47,249 square‐foot joint‐  RFQ
             use facility was held on November 9, 2020.  The celebration was   Architect/Engineer   Nov. 2015   June 2016
             well attended, and the attendees were enthusiastic about the   Selection Process
             facility and its amenities.  An informative video can be found at   Design Development   Mar. 2018   Mar. 2018
             https://www.youtube.com/watch?v=nyCyEN8hxfY&feature=yout  Finalize construction   Fall 2018   Dec. 2018
             u.be                                                     documents
                                                                      Construction contract   Fall 2018   Feb. 2019

                                                                      award
                                                                      Permit Process      Fall 2018   Jan. 2019

                                                                      Construction begins    Fall 2018   Mar. 2019
                                                                      Finalize selection of   Fall 2019   Dec. 2019
                                                                      furniture and
                                                                      equipment
                                                                      Recreation Center   Oct. 2020   Oct. 2020
                                                                      construction
                                                                      complete
                                                                      Move In – Recreation   Oct. 2020   Oct. 2020
                                                                      Center
                                                                      Library construction   Oct. 2020   Oct. 2020
                                                                      complete
                                                                      Move In – Library   Oct. 2020   Oct. 2020