Page 171 - N. Richland Hills Capital Budget
P. 171

Utility Capital Projects
        Department                                             Project Title                         Project Number
        Public Works                         Miscellaneous Water/Sewer Main Replacement (2021)            UT2102
        Project Description
        This is an annual program that is performed by the Public Works Construction Division.  The program will provide for the
        construction of water and wastewater main replacements to include possible development projects.  The project replaces the aging
        and undersized water and wastewater infrastructure. This year's scope is expected to include water/sewer main replacements on the
        following streets: Edinburg Drive (Brookshire to Wakefield), Circle Drive (Susan Lee to Cul-de-sac), Bogart (College Circle to Price),
        Spring Lea Way (Starnes to Lincoln) and Southampton Drive (Wakefield to Chapman).





        Project Justification
        The specific projects are selected based on factors such as ongoing maintenance cost, location of infrastructure, pipe material, and
        diameter of water and wastewater mains. This project provides for the retirement of existing water lines which continue to cause a
        decrease in system capacity and water quality.  This project also replaces the aging wastewater mains that require significant
        maintenance and increased operating costs.  The construction of these lines is completed by the Public Works Construction
        Division.  In addition to the replacement of existing lines, the City's Construction Division also has the capability to handle water and
        wastewater extensions to support lot development, with the costs of those extensions borne by the land owner or developer.  This
        has been particularly helpful for property owners who cannot afford the upcharge levied by contractors for such small projects.

        Note: Project funding source is the Utility Fund (405).








        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Proposed          2020-21       $462,453
        Engineering/Design                                Total                           $462,453
        Land/ROW Acquisition
        Construction               10/2020      09/2021
        Other
        Total Schedule             10/2020      09/2021
        Sources of Funds          To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves                          0        462,453            0             0      $462,453
        Sales Tax
        Other
        Total Funding                    $0        $462,453          $0            $0      $462,453
        Project Costs             To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                      0        462,453            0             0      $462,453
        Other
        Total Costs                       $0       $462,453          $0            $0      $462,453
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2020-21       2021-22      2022-23       2023-24       2024-25     Total Impact
        Amount                           $0            $0            $0            $0            $0            $0
        Total Operating Impact           $0            $0            $0            $0            $0            $0




                                                             165