Page 176 - N. Richland Hills Capital Budget
P. 176

Utility Capital Projects
        Department                                             Project Title                         Project Number
        Public Works                          Telemetric Water Meter Annual Maintenance (2021)            UT2103
        Project Description
        The Telemetric Water Annual Maintenance Program allows the City to continue replacing some of the transponder units and meters
        installed 10 years ago. The new transponder units transmit meter information to a mobile receiver or fixed network reducing and
        eventually eliminating the need for manual readings. Each meter with a transponder costs $285 to replace and the City replaces
        roughly 1,300 per year.






        Project Justification
        This program allows the City to replace transponder and meter units that were installed at the program's inception in 1992-1993.
        The program includes replacement of the Orion Classic Endpoint (CE) water meters with lead-free Smart Endpoints (SE) water
        meters for use in fixed network or mobile reading deployments.
        Note: Project funding source is the Utility Fund (405).














        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Proposed          2020-21       $400,000
        Engineering/Design                                Total                           $400,000
        Land/ROW Acquisition
        Construction               10/2020      09/2021
        Other
        Total Schedule             10/2020      09/2021
        Sources of Funds          To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves                          0        400,000            0             0      $400,000
        Sales Tax
        Other
        Total Funding                    $0        $400,000          $0            $0      $400,000
        Project Costs             To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                      0        400,000            0             0      $400,000
        Other
        Total Costs                       $0       $400,000          $0            $0      $400,000
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2020-21       2021-22      2022-23       2023-24       2024-25     Total Impact
        Amount                           $0            $0            $0            $0            $0            $0
        Total Operating Impact           $0            $0            $0            $0            $0            $0




                                                             170
   171   172   173   174   175   176   177   178   179   180   181