Page 175 - N. Richland Hills Capital Budget
P. 175

Utility Capital Projects
        Department                                             Project Title                         Project Number
        Public Works                               Small Water Main Replacements (2021)                   UT2101
        Project Description
        This is an annual program that is performed by the Public Works Construction Division.  The program replaces old 2" and 4" water
        mains with 6" or larger diameter water pipes. This project provides adequate fire hydrant coverage to areas currently without proper
        coverage.  This project will be expected to provide water main replacement on the following streets: Circleview Drive(Lariat to Shady
        Lake), Davis Boulevard (Woods to Bursey),Meadowbrook Drive (Royal Ridge to Brookridge), and Woodcreek Lane (Lariat to
        Riviera).





        Project Justification
        The specified project replaces aging utility infrastructure, specifically 2" and 4" water mains with new 6" or larger water mains. The
        program also provides adequate fire hydrant coverage to areas currently without proper coverage, this is due to the installation of
        larger diameter mains. Which increases fire protection with the new installation of water hydrants, not previously allowed on smaller
        diameter mains. In addition, this project replaces water mains that have had an abundance of main breaks, resulting in significant
        annual maintenance and increased operating cost. The construction of these mains is completed by the Public Works Construction
        Division.
        Note: Project funding source is the Utility Fund (405).










        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Proposed          2020-21       $462,453
        Engineering/Design                                Total                           $462,453
        Land/ROW Acquisition
        Construction               10/2020      09/2021
        Other
        Total Schedule             10/2020      09/2021
        Sources of Funds          To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves                          0        462,453            0             0      $462,453
        Sales Tax
        Other
        Total Funding                    $0        $462,453          $0            $0      $462,453
        Project Costs             To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                      0        462,453            0             0      $462,453
        Other
        Total Costs                       $0       $462,453          $0            $0      $462,453
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2020-21       2021-22      2022-23       2023-24       2024-25     Total Impact
        Amount                           $0            $0            $0            $0            $0            $0
        Total Operating Impact           $0            $0            $0            $0            $0            $0