Utility Capital Projects
        Department                                             Project Title                         Project Number
        Public Works                                    Matson Drive Sanitary Sewer                      CDBG21
        Project Description
        This is the 46th Year Community Development Block Grant (CDBG) Project.  The project will consist of reconstructing
        approximately 1,300 linear feet of sanitary sewer main.









        Project Justification
        The existing vitrified clay sanitary sewer main serving the residents on the west side of Matson Drive and the east side of US 377 is
        in poor condition and requires significant maintenance as it continues to deteriorate.
        Note:  The Federal / State Grant Funds shown in the "Sources of Funds" are CDBG entitlement funds, which are administered
        entirely by Tarrant County.  This includes design, ultimate contractor selection, construction management and contract close-out
        activities.  As with all previous CDBG projects, the City will have to provide construction inspection services.  No CDBG funds are
        administered by the City; all funds remain with Tarrant County.  The City funds budgeted for in this project are from the Utility Fund
        Reserves (405).










        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services      10/2020      02/2021   Proposed          2020-21        $15,000
        Engineering/Design                                Total                            $15,000
        Land/ROW Acquisition
        Construction               03/2021      09/2021
        Other
        Total Schedule             10/2020      09/2021
        Sources of Funds          To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves                          0         15,000            0             0       $15,000
        Sales Tax
        Other
        Total Funding                    $0        $15,000           $0            $0       $15,000
        Project Costs             To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                      0         15,000            0             0       $15,000
        Other
        Total Costs                       $0        $15,000          $0            $0       $15,000
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2020-21       2021-22      2022-23       2023-24       2024-25     Total Impact
        Amount                           $0            $0            $0            $0            $0            $0
        Total Operating Impact           $0            $0            $0            $0            $0            $0