CITY OF BEDFORD -   FY 20-21 CAPITAL PROJECT SUMMARY

     PROJECT:      Wastewater            PROJECT TYPE: Water/Wastewater       FUNDING SOURCE(S):
     PROJECT TITLE: Wastewater Rehabilitation                                 Water & Sewer Utility Repair  $    550,000

      PROJECT DESCRIPTION:                                                    Certificates of Obligation  $     3,674,219
      This project consists of multiple smaller projects for rehabilitation of the sanitary             $
      sewer main lines. This project will complete point repairs, structural failures, reduce
      infiltration and inflow issues, and in some cases, increase the size of the sewer main            $
      line.
                                                                                                        $
                                                                                          TOTAL FUNDED $        4,224,219
                                                                                             UNFUNDED $        16,164,500

                                                                                          PROJECT TOTAL $      20,388,719
           PROJECT COSTS        Thru                                                               FY 2026 to
          (amounts in 000s)    09/2020    FY 2021     FY 2022    FY 2023     FY 2024    FY 2025   Completion    Total
     Design                     204,219           -          -           -     345,000          -           -    549,219
     Land/Right-of-Way                -           -          -           -           -          -           -          -
     Construction                     -   10,065,000  1,000,000   4,103,700  2,575,800   1,725,000          -  19,469,500

     Landscaping                      -           -          -           -           -          -           -          -
     Equipment & Furnishings          -           -          -           -           -          -           -          -
     Other   System Evaluation  370,000           -          -           -           -          -           -    370,000
           TOTAL COSTS           574,219   10,065,000  1,000,000   4,103,700  2,920,800   1,725,000         -   20,388,719
          SOURCE OF FUNDS       Thru                                                               FY 2026 to
          (amounts in 000s)    09/2020    FY 2021     FY 2022    FY 2023     FY 2024    FY 2025   Completion    Total
     Current Funds                    -     550,000          -           -           -          -           -    550,000

     GO Bonds Issued                  -           -          -           -           -          -           -          -
     GO Bonds Unissued                -           -          -           -           -          -           -          -
     Certificates of Obligation  574,219   3,100,000         -           -           -          -           -   3,674,219
     Other                            -           -          -           -           -          -           -          -

     Unfunded                         -    6,415,000  1,000,000   4,103,700  2,920,800   1,725,000          -  16,164,500
           TOTAL COSTS           574,219   10,065,000  1,000,000   4,103,700  2,920,800   1,725,000         -   20,388,719
                        OPERATING BUDGET IMPACT
                                                                                   MAP/PHOTOGRAPH
         Will Impact                  Annual Cost/(Savings)
         Will Not Impact    Personnel   $
                            Operations  $
       # of Positions:      Capital     $
         Unable to quantify  Total      $
                          IMPACT EXPLANATION

     Wastewater rehabilitation will repair openings in the pipe and
     manholes, decreasing inflow and infiltration, thereby decreasing
     wastewater treatment costs.

         PROJECT SCHEDULE        START             FINISH
     Design                       2019              2024
     Land/Right-of-Way
     Construction                 2020              2025
     Finish Out
     Other                        2019              2025
                                                             369
          TOTAL SCHEDULE          2019              2025