CITY OF BEDFORD -   FY 20-21 CAPITAL PROJECT SUMMARY

     PROJECT:      Generations Park      PROJECT TYPE: Parks/Recreation       FUNDING SOURCE(S):
     PROJECT TITLE: Phase Next Improvement Project                            Series 2008 GO Bond       $      60,000,000

      PROJECT DESCRIPTION:                                                    Series 2019 GO Bond       $       4,500,000
      On November 7, 2017, Bedford voters approved a bond proposition to construct,   Series 2019 Taxable GO Bond $  5,500,000
      improve, renovate and equip park and recreation facilities within the Boys Ranch Park,
      also known as Phase Next. This capital improvement will consist of new ball fields, a   Interest Revenue  $  3,115,235
      multi-generational event facility, an indoor/outdoor aquatic center, as well as a
                                                                                                        $
      proposed art and entertainment facility to be located elsewhere. The City hired a
      project team that consisted of a project manager, civil engineers and architects, and a   TOTAL FUNDED $  73,115,235
      construction manager at risk (CMAR) firm to ensure the capital improvement stays
                                                                                             UNFUNDED $                -
      within budget. The City Council authorized the project team to design and construct
      an art and entertainment facility on the Old Bedford School property for $5.5 million.  PROJECT TOTAL $  73,115,235

           PROJECT COSTS        Thru                                                               FY 2026 to
          (amounts in 000s)    09/2020    FY 2021     FY 2022    FY 2023     FY 2024    FY 2025   Completion    Total
     Design                    2,939,805   1,805,000  1,012,793          -           -          -           -   5,757,598
     Land/Right-of-Way          705,364    1,250,000         -           -           -          -           -   1,955,364
     Construction                60,572   55,351,465  4,850,000          -           -          -           -  60,262,037

     Landscaping                      -           -          -           -           -          -           -          -
     Equipment & Furnishings          -     500,000   4,000,000          -           -          -           -   4,500,000
     Other   Project Management  420,236    110,000     110,000          -           -          -           -    640,236
           TOTAL COSTS          4,125,977  59,016,465  9,972,793         -           -          -           -   73,115,235
          SOURCE OF FUNDS       Thru                                                               FY 2026 to
          (amounts in 000s)    09/2020    FY 2021     FY 2022    FY 2023     FY 2024    FY 2025   Completion    Total
     Current Funds                    -           -          -           -           -          -           -          -

     GO Bonds Issued          70,000,000          -          -           -           -          -           -  70,000,000
     GO Bonds Unissued                -           -          -           -           -          -           -          -
     Certificates of Obligation       -           -          -           -           -          -           -          -
     Other Interest Revenue    3,115,235          -          -           -           -          -           -   3,115,235

     Unfunded                         -           -          -           -           -          -           -          -
           TOTAL COSTS         73,115,235         -           -          -           -          -           -   73,115,235
                        OPERATING BUDGET IMPACT
                                                                                   MAP/PHOTOGRAPH
         Will Impact                  Annual Cost/(Savings)
         Will Not Impact    Personnel   $
                            Operations  $
       # of Positions:      Capital     $
         Unable to quantify  Total      $
                          IMPACT EXPLANATION
     City staff are in the process of evaluating the staffing needs of the
     new facility, but do not have estimates at this time.  Existing
     budgets for utilities and other operational expenses will be
     reallocated to the new facility.
         PROJECT SCHEDULE        START             FINISH
     Design                     FY 17/18          FY 20/21
     Land/Right-of-Way          FY 18/19          FY 20/21
     Construction               FY 20/21          FY 21/22
     Finish Out                 FY 21/22          FY 21/22
     Other                      FY 17/18          FY 21/22
                                                             365
          TOTAL SCHEDULE        FY 17/18          FY 21/22