Page 399 - City of Bedford FY21 Budget
P. 399

TOTAL EST. CURRENTLY                                             FUNDING
        PROJECT                              COST    FUNDED  FY 19/20  FY 20/21  FY 21/22  FY 22/23  FY 23/24  FY 24/25  SOURCE
          Bell Manor North Addition Sewer Main Rehabilitation
          (Savannah Way)                       350,000  Yes                             350,000                2
          Harwood Terrace Addition Sewer Main Rehabilitation
          (Steeplechase Drive to Simpson Terrace)  410,000  Yes                         410,000                2
          Wastewater Rehabilitation 2023-01 (Basins H4, H5, H6 and
          H7 from Belle Street to Piipeline Road / Sulpur Branch
          Trunk Sewer from Hust Drive to Pipeline Road / Pipeline
          Road Trunk Sewer from Glenda Drive to Arwine Cemetary
          Road / Monette Drive (Wade Drive to Circle Lane)  2,000,000  No              2,000,000              TBD
          Deuce Drive Sewer Main Rehabilitation - Tennis Drive to
          Brown Trail                          170,200  No                              170,200               TBD
          Sanitary Sewer Creek Crossings (various)  500,000  No                         500,000               TBD
          Murphy Drive Sewer Main Rehabilitation - Harwood Road
          to Cheeksparger                     2,070,000  No                                     345,000  1,725,000  TBD
          Basin 19.1W - Warwickshire to SH 183  421,000  Yes                                    421,000        2
      528  Rehab Sewer Mains in Sulphur Branch Drainage Area  1,000,000  No                    1,000,000      TBD
          Rollingwood and Lincolnshire Sewer Main Rehabilitation  750,000  No                   750,000       TBD
          Bedford Road - Central to SH 183     404,800  No                                      404,800       TBD
        DRAINAGE
        Drainage System Study                  900,000  Yes            900,000                                 1
        Sulphur Branch
      505  Channel Improvements - SH183 to Bedford Road   1,700,000  No       1,700,000                       TBD
        Sulphur Branch Tributary
          Briar Drive, Shirley Way, Circle Lane, Schumac Lane and
      505  Donna Lane Culvert / Bridge        2,200,000  No                            2,200,000              TBD
        Erosion Control Sulphur Branch & Sulphur Branch Tributary
      505  Erosion Control - Brookhollow Park  4,770,688  Partial  1,870,688  2,900,000                      1 & TBD
        Erosion Control Various Other Channels
          Brookwood Stream                     950,000  Yes            950,000                                 1
          Hurricane Creek Entrance Ramps (South of Commerce Place
          and East of Hospital Parkway)        400,000  No                              400,000               TBD
          Cheeksparger Channel between Murphy and Rolling
          Meadows                              230,000  Yes                                     230,000        1
          Little Bear Creek South of Cheek Sparger  230,000  Yes                                230,000        1
        ROADS

          Cheeksparger signal light installation and intersection
          improvements                         325,260  Yes    325,260                                         4
          Bedford Court East Reconstruction - Brown Trail to Hurst
          City Limits                          489,349  Yes    489,349                                        1 & 4
          Rankin Drive Reconstruction - Forest Ridge to Brook
          Hollow Park                          450,000  Yes            450,000                                 4
          Shady Lake Reconstruction - Shady Brook to Lakeview  275,000  No     275,000                        TBD
          Briar Reconstruction                2,000,000  No                   2,000,000                       TBD
          Monette Drive - Wade Drive to Circle Lane  1,200,000  No            1,200,000                       TBD
          Robindale Drive Reconstruction - Wade to Martha  450,000  No         450,000                        TBD
          Murphy Drive Reconstruction - Harwood Road to
          Cheeksparger                        3,910,000  No                   3,910,000                       TBD
          Deuce Drive Reconstruction - Tennis Drive to Brown Trail  345,000  No         345,000               TBD

        TOTALS                             $151,102,799      $9,456,033  $74,266,465  $41,874,351  $14,247,700  $7,493,800  $3,525,000