Infrastructure


                                      Goal 1: Plan, Manage, and Maintain Public Assets
                                    Objective 2: Maintain City Standards for all Municipal Buildings
                       Project                   Performance Measure(s)            City Service Team (Department)
             Core   Fire Station 1 Rebuild     Overall satisfaction of project   Shared Services (AM) and
             INF                           management                           Neighborhood Services (Fire)
             1.2.1                         Project completion on time and at budget
             Summary:
                                                                  Milestone           Estimated      Actual
             To handle the growing needs of the community,                           Completion   Completion
             and surrounding business districts, the Arlington   Initial Project     Dec. 2018    Dec. 2018
             Fire Department has partnered with Asset     schedule/development phase
             Management to re‐design the existing Fire    Architect/engineer RFQ     Oct. 2019    Oct. 2019
             Station #1 located at 401 W. Main St.  Station #1   Architect/engineer selection   Nov. 2019   Dec. 2019
             is at the heart of the City’s downtown area and   process
             one of the oldest facilities currently managed by   Architect/Engineer contract   Dec. 2019   Jan. 2019
             the Fire Department and was most recently    approval and execution
             remodeled in 1987.                           Manager at Risk contract   Dec. 2019    Jan. 2020
                                                          approval and execution
             Update:                                      Construction Management at   Fall 2020   Feb. 2020
                   th
             In the 4  quarter of FY 2020, City Council   Risk process
             approved to move forward with design. The
                                                          Design                     TBD
             architects are revising the design and project   Guaranteed Maximum Price   TBD
             schedule.
                                                          to Council

                                                          Permit review process      TBD
                                                          Council approval           TBD
                                                          Vacate station             TBD

                                                          Demolition phase           TBD
                                                          Construction phase         TBD

                                                          Move in                    TBD