Infrastructure


                                      Goal 1: Plan, Manage, and Maintain Public Assets
                                    Objective 2: Maintain City Standards for all Municipal Buildings
                        Project                     Performance Measure(s)           City Service Team (Department)
             Core    Tierra Verde Golf Course     Overall satisfaction of project management   Shared Services (AM) and
             INF    / Ventana Grille –       Project completion on time and at budget   Neighborhood Services (Parks)
             1.2.3   Geothermal HVAC         Citizen satisfaction with overall quality of
                    System                   parks and recreation programs and classes
             Summary:
                                                                   Milestone           Estimated      Actual
             The existing geothermal HVAC system currently                            Completion   Completion
             operating at Tierra Verde Golf Clubhouse and   Identify location of existing   Jan. 2019   Feb. 2019
             Ventana Grille is beginning to fail causing   piping and thermal wells
             insufficient cooling throughout the facility. Asset   RFQ process for Mechanical   Feb. 2019   May 2019
             Management will collaborate with the Parks    Engineering firm
             Department to determine the best cost‐effective   Engineering firm selection   Feb. 2019   June 2019
             approach to either improve the existing       process
             geothermal system or recommend replacement
                                                           Council approval of        Aug. 2019    Aug. 2019
             with a conventional HVAC system. As part of the   Engineering firm
             project, temporary temperature control measures   Design, including review of   Fall 2019   Jan. 2020
             will be considered as needed.
                                                           recommended options
                                                           Bidding Process            Spring 2020   Mar. 2020
             The time frame for the request for qualification for   Permit review process    TBD 2020   Apr. 2020
             mechanical engineer was revised from February   Contractor Council approval   TBD 2020   Apr. 2020
             2019 to May of 2019.  Additional time was needed   Construction phase    Sept.  2020   Oct. 2020
             to complete a feasibility study to define the scope
             of work.

             Update:
                   th
             In the 4  quarter of FY 2020, CMP Construction
             completed all work on the HVAC system. During
             testing of the system, it was discovered the two
             sensor boards were defective and had to be re‐
             ordered. Final acceptance of the work is expected
             in early October.