                           Goal 1: Ensure Availability of Information, Programs, and City Services
                        Objective 1: Provide for the Efficient Access and Appropriate Management of the City’s Data
                          Project                  Performance Measure(s)        City Service Team (Department)
             PTW   Enterprise IT Project (FY 2019) –   Project Completion   Shared Services (IT and Municipal Court)
             1.1.4  Tyler Content Management
                   (Laserfiche replacement)
             Summary:
                                                                   Milestone          Target Date      Status
             The Court Tyler Content Management project will   Charter Development   1  Qtr. FY 2019   Complete
                                                                                    st
                                                                                    th
             oversee the planning and implementation of Tyler   Staff Report Approval   4  Qtr. FY 2019    Complete
             Content Manager (TCM) application suite, the     by Council
             conversion and migration of millions of Court records   Procurement   4  Qtr. FY 2019    Complete
                                                                                    th
             to the new system and to retire the Courts Laserfiche   Project Planning   1  Qtr. FY 2020   In Progress
                                                                                    st
             system.                                          System               1  Qtr. FY 2021   In Progress
                                                                                    st
                                                              implementation and
             Update:                                          configuration
             The project team and vendor continue to hold weekly   Document Conversion   1  Qtr. FY 2021   In Progress
                                                                                    st
             work sessions to monitor and execute the project.    and Migration
             Tyler has been dealing with a corporate ransom ware                    nd
                                                              Staff Training / Go Live  2  Qtr. FY 2021
             security breach which has stalling all development   Project Close    2  Qtr. FY 2021
                                                                                    nd
             efforts that were underway.  Prior to development
             restarting – the City will make a fresh copy of the Court   Notes:
             Laserfiche database and a full copy of all documents.    The remaining milestones will be updated after vendor
             The refresh will allow for control counts to be
                                                             statement of work and project schedule has been negotiated.
             determined and provided to the vendor prior to
                                                             This schedule refinement extended the overall timeline for
             resuming document migration efforts.            project closure.