Page 394 - FY 2009 Proposed Budget
P. 394

Put Technology to Work


                           Goal 1: Ensure Availability of Information, Programs, and City Services
                        Objective 1: Provide for the Efficient Access and Appropriate Management of the City’s Data
                        Project                 Performance Measure(s)           City Service Team (Department)
             PTW   ERP System Plan and                                      Finance (Purchasing), Shared Services (HR
             1.1.1  Assessment                                              and IT)
             Summary:
                                                                      Milestone          Estimated    Actual
             The City of Arlington’s current ERP solution will                          Completion  Completion
             become unsupported within the next 4 years.  City   Solicit RFQ for Consultant   10/1/2018   12/5/2018
             staff have been informed that the next version of   Services
             Lawson will be a rewritten program package that will   Award contract to firm for   2/19/2019   3/19/2019
             require a full‐scale conversion as opposed to a   ERP consulting services
             standard upgrade/migration.                     Needs Assessment Begins    6/10/2019   10/1/2019
                                                             Present Final Assessment   9/13/2019   10/29/2019
             Through a standardized method, the Finance and   Report to Council Committee
             Human Resources Departments will conduct a full   Solicit RFP for an ERP Solution   12/2/2019   1/15/2020
             process and needs review to determine what is the   Conduct and Score Product   6/30/2020   6/24/2020
             best ERP solution for the Finance and HR staff to   Demos
             perform their day‐to‐day operations and interactions   Award contract for new ERP   9/28/2020   9/28/2020
             both inside and outside of the City.            provider
                                                             Begin implementation of new   10/1/2020   10/1/2020
             Update:                                         solution
             The contract for the City’s new ERP Solution was
             awarded to Workday/Accenture on September 28,
             2020.  Implementation of the new system will begin in
             FY 2021.