Page 368 - FY 2009 Proposed Budget
P. 368
Champion Great Neighborhoods
Goal 2: Expand and Enhance the City’s Image
Objective 2: Develop a Sense of Place
Project Performance Measure(s) City Service Team (Department)
CGN Park Improvement Projects Timeliness of completion Neighborhood Services (Parks)
2.2.3 Overall satisfaction with programs
and facilities
Summary:
Milestones Estimated Actual Estimated Actual
Julia Burgen Park /TxDOT Grant (New Start Start Completion Completion
Development):
Julia Burgen Jan. 2019 Feb. Aug. 2022
There is an existing 1.06 miles of trail currently in
Julia Burgen Park. This project involves adding Park TxDOT 2019
approximately .3 miles of concrete trail that will River Legacy Apr. Feb. 2022
provide a connection from the existing trail to the Park 2018
on‐street bike path along Pecan Street, ultimately Lynn Creek Feb. 2019 June Mar. 2020 May 2020
linking to the UTA campus. Project includes the Linear Park 2019
preparation of bid documents and construction of Bowman Apr. 2020 Oct. Dec. 2020
new trail. Branch 2019
Linear Park
Consultant has been selected through RFQ process.
Design process is estimated to take approximately Lynn Creek Linear Park/TxDOT Grant (New Development):
1‐1/2 years to complete due to TXDOT Construction of approximately 1.5 miles of 12’ wide trail from Butter
requirements associated with the hydraulic and
Cup Lane to New York Avenue.
environmental review. Construction is scheduled
nd
to begin in the 2 quarter of 2021. Construction contract has been approved by Council and contract
execution is complete. Construction began June 2019.
Update: A new alignment has been approved by
TXDOT, NTCOG, and UTA, and subsequently the
Update: The project has been completed.
related modified AFA agreement and design
contract by City Council. New survey and realty Bowman Branch Linear Park (New Development):
research have begun. Construction of approximately 1.4 miles of 12’ wide trail from Webb
Community Park to New York Avenue.
River Legacy Park (Re‐development):
Realignment of approximately 1.3 miles of 12’ wide
Construction documents are complete. Construction scheduled to
concrete trail. Project includes the preparation of begin October 2019.
bid documents and construction of new trail.
Update: Construction is progressing as scheduled, including the
Project has been delayed pending the completion
completion of the first section from Webb Community park to
of a wetland delineation associated with the new
Webb Ferrell Rd. Crews are currently working on the section
proposed trail alignment. between Webb Ferrell rd. and S. Collins St.
Update: The Texas Historical Commission (THC) is
requiring an archeological survey and Texas
Antiquities Permit, thus requiring a design contract
modification to coordinate this unanticipated work
and adjust the design accordingly. The modification
is scheduled for City Council approval in October.
17