                                   City of Southlake FY 2020 CIP Project Status Form

                     FM 1938 at West Continental Boulevard Intersection Improvements (RIFF 1 Companion)

              DEPARTMENT: Public Works
              PROJECT
              LOCATION:   FM 1938 at W. Continental Boulevard

              PROJECT TIMELINE: Oct 2019  to  Sept 2020
              DESCRIPTION:
               Funding is requested for right of way, new traffic signal, right turn lane and other paving
               improvements to improve alignment of this intersection based on recommendations of
               preliminary engineering study of this intersection. Drainage improvements will also be
               included with this project, specifically the improvement of Critical Drainage Structure
               #18.






                                                                       New Request     Continuation Project  Joint Use
               JUSTIFICATION:                                          Mandated /    Replacement / Major   Community
                                                                       Public Health /   Rehab or Protection      Need / Service
               These improvements will help alleviate current traffic backups during peak hours on  Safety  of Capital Stock  Enhancement
               westbound Continental Boulevard at FM 1938.
                                                                        Compliant with 2030/2035 Comprehensive Plan Element?
                                                                       List (incl ref #):
               ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:          COMPANION PROJECT? If yes, please explain:
               Roadway will remain at current capacity, resulting in the continual increase in traffic  Roadway Impact Fee Fund RIFF1
               congestion during peak hours.
                                                                        REVENUE GENERATING? If yes, please explain:
               STRATEGIC FOCUS AREA: Mobility, Infrastructure
                                                                        N/A
               FUND:  General, Roadway Impact Fee
                                                        EXPENDITURE SCHEDULE
                   PROJECT ELEMENT  TOTAL PRIOR  2020    2021     2022     2023      2024    UNFUNDED    TOTAL
                PLANNING / FEASIBILITY STUDY                                                               0
                    ENGINEERING & DESIGN        200                                                       200
                               LAND                                                                        0
                             TESTING                                                                       0
                         CONSTRUCTION           700      1,100                                            1,800
                              OTHER                                                                        0
                              TOTAL    0        900      1,100     0        0        0          0         2,000
                                                         OPERATIONAL IMPACT
                   PROJECT ELEMENT  TOTAL PRIOR  2020    2021     2022     2023      2024    UNFUNDED    TOTAL
                     MAINTENANCE COSTS                    10       10       10       10        10          50
                      PERSONNEL COSTS                                                                      0
                              TOTAL    0         0        10       10       10       10        10          50
                                                          FUNDING SCHEDULE
                   FUNDING SOURCE  TOTAL PRIOR  2020     2021     2022     2023      2024    UNFUNDED    TOTAL
                         GENERAL FUND           900      1,100                                            2,000
                               CCPD                                                                        0
                               CEDC                                                                        0
                HOTEL OCCUPANCY TAX FUND                                                                   0
                 PARK DEDICATION FEE FUND                                                                  0
                        PUBLIC ART FUND                                                                    0
                 ROADWAY IMPACT FEE FUND  800   300      300                                              1,400
                SANITARY SEWER IMPACT FEE                                                                  0
                               SPDC                                                                        0
                               SWUS                                                                        0
                          UTILITY FUND                                                                     0
                   WATER IMPACT FEE FUND                                                                   0
                              TOTAL   800      1,200     1,400     0        0        0          0         3,400
               CCPD: CRIME CONTROL & PREVENTION DISTRICT                           SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
               CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                      SWUS: STORMWATER UTILITY SYSTEM FUND

                                    Funding is represented in thousands of dollars (000s).  Example:  3,776 = $3,776,000