Page 366 - Southlake FY20 Budget
P. 366

General Fund
                                                                                                                    CIP

                                                                                                         GEnERAL FUnD


                                City of Southlake FY 2020 CIP Project Status Form

                                            Citywide Pathway Improvements

           DEPARTMENT: Public Works
           PROJECT
           LOCATION:   Various Locations within the City

           PROJECT TIMELINE: Oct 2019  to  Sept 2020
           DESCRIPTION:
           Funding is requested for right of way, engineering design and construction of sidewalks
           at various locations throughout the City. Projects are recommended by staff via the
           Master Pathways Plan and approved by City Council as part of the annual sidewalk
           priority list.







                                                                    New Request     Continuation Project  Joint Use
           JUSTIFICATION:                                           Mandated /    Replacement / Major   Community
                                                                    Public Health /
                                                                                  Rehab or Protection
           Providing sidewalks for pedestrian safety by keeping foot traffic off City streets has     Safety  of Capital Stock     Need / Service
                                                                                                   Enhancement
           been identified as Citywide gap issue.
                                                                     Compliant with 2030/2035 Comprehensive Plan Element?
                                                                    List (incl ref #):
           ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
           Failure to fund could result in continued safety hazard for pedestrians in certain areas  N/A
           of the City.
                                                                    REVENUE GENERATING? If yes, please explain:
           STRATEGIC FOCUS AREA: Mobility, Infrastructure
                                                                    N/A
           FUND:  General
                                                     EXPENDITURE SCHEDULE
               PROJECT ELEMENT  TOTAL PRIOR  2020     2021     2022     2023     2024     UNFUNDED    TOTAL
            PLANNING / FEASIBILITY STUDY                                                               0
                ENGINEERING & DESIGN                                                                   0
                            LAND                                                                       0
                          TESTING                                                                      0
                     CONSTRUCTION  4,176    300       350      350      350      350        400       6,276
                           OTHER                                                                       0
                           TOTAL  4,176     300       350      350      350      350        400       6,276
                                                     OPERATIONAL IMPACT
               PROJECT ELEMENT  TOTAL PRIOR  2020     2021     2022     2023     2024    UNFUNDED     TOTAL
                  MAINTENANCE COSTS          10       10       10       10        10        10         60
                   PERSONNEL COSTS                                                                     0
                           TOTAL    0        10       10       10       10        10        10         60
                                                      FUNDING SCHEDULE
                FUNDING SOURCE  TOTAL PRIOR  2020     2021     2022     2023     2024     UNFUNDED    TOTAL
                     GENERAL FUND  4,176    300       350      350      350      350        400       6,276
                           CCPD                                                                        0
                           CEDC                                                                        0
             HOTEL OCCUPANCY TAX FUND                                                                  0
              PARK DEDICATION FEE FUND                                                                 0
                    PUBLIC ART FUND                                                                    0
             ROADWAY IMPACT FEE FUND                                                                   0
             SANITARY SEWER IMPACT FEE                                                                 0
                           SPDC                                                                        0
                           SWUS                                                                        0
                       UTILITY FUND                                                                    0
               WATER IMPACT FEE FUND                                                                   0
                           TOTAL  4,176     300       350      350      350      350        400       6,276
           CCPD: CRIME CONTROL & PREVENTION DISTRICT                            SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
           CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                      SWUS: STORMWATER UTILITY SYSTEM FUND
                                Funding is represented in thousands of dollars (000s).  Example:  3,776 = $3,776,000