                                City of Southlake FY 2020 CIP Project Status Form

                       Street Rehabilitation Required by Pavement Management Application (PMA)

           DEPARTMENT: Public Works
           PROJECT
           LOCATION:   Various Locations within the City

           PROJECT TIMELINE: Oct 2019  to  Sept 2020
           DESCRIPTION:
           Funding is requested to continue the citywide pavement rehabilitation program. This
           program is based on an annual condition assessment conducted by a third party.









                                                                    New Request     Continuation Project  Joint Use
           JUSTIFICATION:                                           Mandated /    Replacement / Major   Community
                                                                    Public Health /      Rehab or Protection      Need / Service
           This assessment feeds the City's Pavement Quality Index (PQI) which is the  Safety  of Capital Stock  Enhancement
           foundation for prioritizing pavement rehabilitation projects. The PQI is also an
           essential element of the City's annual financial audit.     Compliant with 2030/2035 Comprehensive Plan Element?
                                                                    List (incl ref #):
           ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
           Not funding the Pavement Management Program could lead to increased roadway  N/A
           deterioration.
                                                                    REVENUE GENERATING? If yes, please explain:
           STRATEGIC FOCUS AREA: Infrastructure, Mobility
                                                                    N/A
           FUND:  General
                                                     EXPENDITURE SCHEDULE
               PROJECT ELEMENT  TOTAL PRIOR  2020     2021     2022     2023     2024     UNFUNDED    TOTAL
            PLANNING / FEASIBILITY STUDY                                                               0
                ENGINEERING & DESIGN                                                                   0
                            LAND                                                                       0
                          TESTING                                                                      0
                     CONSTRUCTION  13,554   1,100    1,200    1,300    1,400     1,500     1,600      21,654
                           OTHER                                                                       0
                           TOTAL  13,554    1,100    1,200    1,300    1,400     1,500     1,600      21,654
                                                     OPERATIONAL IMPACT
               PROJECT ELEMENT  TOTAL PRIOR  2020     2021     2022     2023     2024    UNFUNDED     TOTAL
                  MAINTENANCE COSTS                                                                    0
                   PERSONNEL COSTS                                                                     0
                           TOTAL    0        0        0         0        0        0         0          0
                                                      FUNDING SCHEDULE
                FUNDING SOURCE  TOTAL PRIOR  2020     2021     2022     2023     2024     UNFUNDED    TOTAL
                     GENERAL FUND  13,554   1,100    1,200    1,300    1,400     1,500     1,600      21,654
                           CCPD                                                                        0
                           CEDC                                                                        0
             HOTEL OCCUPANCY TAX FUND                                                                  0
              PARK DEDICATION FEE FUND                                                                 0
                    PUBLIC ART FUND                                                                    0
             ROADWAY IMPACT FEE FUND                                                                   0
             SANITARY SEWER IMPACT FEE                                                                 0
                           SPDC                                                                        0
                           SWUS                                                                        0
                       UTILITY FUND                                                                    0
               WATER IMPACT FEE FUND                                                                   0
                           TOTAL  13,554    1,100    1,200    1,300    1,400     1,500     1,600      21,654
           CCPD: CRIME CONTROL & PREVENTION DISTRICT                            SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
           CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                      SWUS: STORMWATER UTILITY SYSTEM FUND
                                Funding is represented in thousands of dollars (000s).  Example:  3,776 = $3,776,000