Page 420 - City of Bedford FY20 Approved Budget
P. 420

CITY OF BEDFORD -   FY 19-20 CAPITAL PROJECT SUMMARY

     PROJECT:      Street                PROJECT TYPE: SIEDC 4B Corp.         FUNDING SOURCE(S):
     PROJECT TITLE: Street Improvement                                        SIEDC                     $        753,688

      PROJECT DESCRIPTION:                                                    CDBG                      $        155,000
      This project consists of the reconstruction of various streets, to include Rankin Drive   GO Bond  $        71,612
      from Forest Ridge Drive to Brook Hollow Park, Shady Lake from Shady Brook to
      Lakeview, Robindale Drive from Wade to Martha, Deuce Drive from Tennis to Brown                   $
      Trail, Murphy Drive from Harwood Road to Cheeksparger Road, Briar Drive from Forest
                                                                                                        $
      Ridge Drive to Circle Lane, Bedford Court East from Brown Trail to Hurst City limit, and
      Monette Drive from Wade to Circle Lane.                                             TOTAL FUNDED $         980,300
                                                                                             UNFUNDED $         8,894,000

                                                                                          PROJECT TOTAL $       9,874,300
           PROJECT COSTS        Thru                                                               FY 2025 to
          (amounts in 000s)    09/2019    FY 2020     FY 2021    FY 2022     FY 2023    FY 2024   Completion    Total
     Design                           -      45,000          -           -           -          -           -     45,000
     Land/Right-of-Way                -           -          -           -           -          -           -          -
     Construction               508,700     426,600   7,280,000   1,614,000          -          -           -   9,829,300

     Landscaping                      -           -          -           -           -          -           -          -
     Equipment & Furnishings          -           -          -           -           -          -           -          -
     Other                            -           -          -           -           -          -           -          -
           TOTAL COSTS           508,700     471,600   7,280,000   1,614,000         -          -           -    9,874,300
          SOURCE OF FUNDS       Thru                                                               FY 2025 to
          (amounts in 000s)    09/2019    FY 2020     FY 2021    FY 2022     FY 2023    FY 2024   Completion    Total
     Current Funds              508,700     244,988          -           -           -          -           -    753,688

     GO Bonds Issued                  -      71,612          -           -           -          -           -     71,612
     GO Bonds Unissued                -           -          -           -           -          -           -          -
     Certificates of Obligation       -           -          -           -           -          -           -          -
     Other CDBG                       -     155,000          -           -           -          -           -    155,000

     Unfunded                         -           -   7,280,000   1,614,000          -          -           -   8,894,000
           TOTAL COSTS           508,700     471,600   7,280,000   1,614,000         -          -           -    9,874,300
                        OPERATING BUDGET IMPACT
                                                                                   MAP/PHOTOGRAPH
         Will Impact                  Annual Cost/(Savings)
         Will Not Impact    Personnel   $
                            Operations  $
       # of Positions:      Capital     $
         Unable to quantify  Total      $
                          IMPACT EXPLANATION







         PROJECT SCHEDULE        START             FINISH
     Design                       2018              2021
     Land/Right-of-Way
     Construction                 2019              2022
     Finish Out
     Other
                                                             387
          TOTAL SCHEDULE          2019              2022