CITY OF BEDFORD -   FY 19-20 CAPITAL PROJECT SUMMARY

     PROJECT:      Wastewater            PROJECT TYPE: Water/Wastewater       FUNDING SOURCE(S):
     PROJECT TITLE: Wastewater Rehabilitation                                 Certificates of Obligation  $     5,419,700

      PROJECT DESCRIPTION:                                                    Utility Repair Fund       $        578,333
      This project consists of multiple smaller projects for rehabilitation of the sanitary             $
      sewer main lines. This project will complete point repairs, structural failures, reduce
      infiltration and inflow issues, and in some cases, increase the size of the sewer main            $
      line.
                                                                                                        $
                                                                                          TOTAL FUNDED $        5,998,033
                                                                                             UNFUNDED $        13,553,800

                                                                                          PROJECT TOTAL $      19,551,833
           PROJECT COSTS        Thru                                                               FY 2025 to
          (amounts in 000s)    09/2019    FY 2020     FY 2021    FY 2022     FY 2023    FY 2024   Completion    Total
     Design                           -           -          -           -           -          -           -          -
     Land/Right-of-Way                -           -          -           -           -          -           -          -
     Construction               578,333    5,419,700  12,590,000   963,800           -          -           -  19,551,833

     Landscaping                      -           -          -           -           -          -           -          -
     Equipment & Furnishings          -           -          -           -           -          -           -          -
     Other                            -           -          -           -           -          -           -          -
           TOTAL COSTS           578,333    5,419,700  12,590,000   963,800          -          -           -   19,551,833
          SOURCE OF FUNDS       Thru                                                               FY 2025 to
          (amounts in 000s)    09/2019    FY 2020     FY 2021    FY 2022     FY 2023    FY 2024   Completion    Total
     Current Funds              578,333           -          -           -           -          -           -    578,333

     GO Bonds Issued                  -           -          -           -           -          -           -          -
     GO Bonds Unissued                -           -          -           -           -          -           -          -
     Certificates of Obligation       -    5,419,700         -           -           -          -           -   5,419,700
     Other                            -           -          -           -           -          -           -          -

     Unfunded                         -           -  12,590,000    963,800           -          -           -  13,553,800
           TOTAL COSTS           578,333    5,419,700  12,590,000   963,800          -          -           -   19,551,833
                        OPERATING BUDGET IMPACT
                                                                                   MAP/PHOTOGRAPH
         Will Impact                  Annual Cost/(Savings)
         Will Not Impact    Personnel   $
                            Operations  $
       # of Positions:      Capital     $
         Unable to quantify  Total      $
                          IMPACT EXPLANATION

     Completing repairs to the sanitary sewer system decreases the
     inflow and infiltration, decreasing the cost to the City for
     wastewater treatment.

         PROJECT SCHEDULE        START             FINISH
     Design                       2017            Ongoing
     Land/Right-of-Way
     Construction                 2017            Ongoing
     Finish Out
     Other
                                                             383
          TOTAL SCHEDULE          2017            Ongoing