CITY OF BEDFORD -   FY 19-20 CAPITAL PROJECT SUMMARY

     PROJECT:      SWIFT 16-03           PROJECT TYPE: Water/Wastewater       FUNDING SOURCE(S):
     PROJECT TITLE: Automated Meter Reading (AMR) System Project              Utility Repair            $        196,932

      PROJECT DESCRIPTION:                                                    Certificates of Obligation  $    13,415,847
      This project consists of the replacement of all meters within the distribution system             $
      with ultrasonic meters and reading devices that utilize cell phone service. It will also
      reconstruct the current meter vaults to current standards. This project includes the              $
      software for billing and customer usage to follow the consumption.
                                                                                                        $
                                                                                          TOTAL FUNDED $       13,612,779
                                                                                             UNFUNDED $                -

                                                                                          PROJECT TOTAL $      13,612,779
           PROJECT COSTS        Thru                                                               FY 2025 to
          (amounts in 000s)    09/2019    FY 2020     FY 2021    FY 2022     FY 2023    FY 2024   Completion    Total
     Design                     196,932           -          -           -           -          -           -    196,932
     Land/Right-of-Way                -           -          -           -           -          -           -          -
     Construction             13,415,847          -          -           -           -          -           -  13,415,847

     Landscaping                      -           -          -           -           -          -           -          -
     Equipment & Furnishings          -           -          -           -           -          -           -          -
     Other                            -           -          -           -           -          -           -          -
           TOTAL COSTS         13,612,779         -           -          -           -          -           -   13,612,779
          SOURCE OF FUNDS       Thru                                                               FY 2025 to
          (amounts in 000s)    09/2019    FY 2020     FY 2021    FY 2022     FY 2023    FY 2024   Completion    Total
     Current Funds              196,932           -          -           -           -          -           -    196,932

     GO Bonds Issued                  -           -          -           -           -          -           -          -
     GO Bonds Unissued                -           -          -           -           -          -           -          -
     Certificates of Obligation  13,415,847       -          -           -           -          -           -  13,415,847
     Other                            -           -          -           -           -          -           -          -

     Unfunded                         -           -          -           -           -          -           -          -
           TOTAL COSTS         13,612,779         -           -          -           -          -           -   13,612,779
                        OPERATING BUDGET IMPACT
                                                                                   MAP/PHOTOGRAPH
         Will Impact                  Annual Cost/(Savings)
         Will Not Impact    Personnel   $
                            Operations  $
       # of Positions:      Capital     $
         Unable to quantify  Total      $
                          IMPACT EXPLANATION
     The ultrasonic meters register lower flows than the turbine meters
     used in the system. Detection of lower flows allow for the billing of
     small water leaks in the customer service line. The meter reading
     contract will be discontinued and the funds saved to be used for
     future communication costs for the meter reading system.
         PROJECT SCHEDULE        START             FINISH
     Design                      12/2015           04/2019
     Land/Right-of-Way
     Construction                07/2017           04/2019
     Finish Out
     Other
                                                             380
          TOTAL SCHEDULE         12/2015           04/2019