CITY OF BEDFORD -   FY 19-20 CAPITAL PROJECT SUMMARY

     PROJECT:      SWIFT                 PROJECT TYPE: Water/Wastewater       FUNDING SOURCE(S):
     PROJECT TITLE: SWIFT Water Line Replacement                              Certificates of Obligation  $    28,777,350

      PROJECT DESCRIPTION:                                                                              $
      Many of the water lines in the City of Bedford are 30 plus years old and are rapidly              $
      deteriorating.  Many of the water lines that will be replaced have had multiple breaks,
      placing customers without service and water loss. This large project will consist of              $
      multiple smaller projects for the replacement of these lines.
                                                                                                        $
                                                                                          TOTAL FUNDED $       28,777,350
                                                                                             UNFUNDED $         6,056,445

                                                                                          PROJECT TOTAL $      34,833,795
           PROJECT COSTS        Thru                                                               FY 2025 to
          (amounts in 000s)    09/2019    FY 2020     FY 2021    FY 2022     FY 2023    FY 2024   Completion    Total
     Design                           -           -          -           -           -          -           -          -
     Land/Right-of-Way                -           -          -           -           -          -           -          -
     Construction             15,839,795   9,990,000  5,593,000   3,411,000          -          -           -  34,833,795

     Landscaping                      -           -          -           -           -          -           -          -
     Equipment & Furnishings          -           -          -           -           -          -           -          -
     Other                            -           -          -           -           -          -           -          -
           TOTAL COSTS         15,839,795   9,990,000  5,593,000   3,411,000         -          -           -   34,833,795
          SOURCE OF FUNDS       Thru                                                               FY 2025 to
          (amounts in 000s)    09/2019    FY 2020     FY 2021    FY 2022     FY 2023    FY 2024   Completion    Total
     Current Funds                    -           -          -           -           -          -           -          -

     GO Bonds Issued                  -           -          -           -           -          -           -          -
     GO Bonds Unissued                -           -          -           -           -          -           -          -
     Certificates of Obligation  15,839,795  9,990,000  2,947,555        -           -          -           -  28,777,350
     Other                            -           -          -           -           -          -           -          -

     Unfunded                         -           -   2,645,445   3,411,000          -          -           -   6,056,445
           TOTAL COSTS         15,839,795   9,990,000  5,593,000   3,411,000         -          -           -   34,833,795
                        OPERATING BUDGET IMPACT
                                                                                   MAP/PHOTOGRAPH
         Will Impact                  Annual Cost/(Savings)
         Will Not Impact    Personnel   $
                            Operations  $
       # of Positions:      Capital     $
         Unable to quantify  Total      $
                          IMPACT EXPLANATION


     Replacement of water mains will decrease the amount of breaks to
     the water distribution system.


         PROJECT SCHEDULE        START             FINISH
     Design                       2013              2020
     Land/Right-of-Way
     Construction                 2016              2029
     Finish Out
     Other
                                                             381
          TOTAL SCHEDULE          2013              2029