Page 409 - City of Bedford FY20 Approved Budget
P. 409

CITY OF BEDFORD -   FY 19-20 CAPITAL PROJECT SUMMARY

     PROJECT:      Boys Ranch Park       PROJECT TYPE: Parks/Recreation       FUNDING SOURCE(S):
     PROJECT TITLE: Boys Ranch Park Phase Next Improvement Project            Series 2018 GO Bond       $      60,000,000

      PROJECT DESCRIPTION:                                                    Series 2019 GO Bond       $       4,500,000
      On November 7, 2017, Bedford voters approved a bond proposition to construct,   Series 2019 Taxable GO Bond $  5,500,000
      improve, renovate and equip park and recreation facilities within the Boys Ranch Park,
      also known as Phase Next. This capital improvement will consist of new ball fields, a             $
      multi-generational event facility, an indoor/outdoor aquatic center, as well as a
                                                                                                        $
      proposed art and entertainment facility to be located elsewhere. The City hired a
      project team that consisted of a project manager, civil engineers and architects, and a   TOTAL FUNDED $  70,000,000
      construction manager at risk (CMAR) firm to ensure the capital improvement stays
                                                                                             UNFUNDED $
      within budget.  The City Council authorized the project team to design and construct
      an art and entertainment facility on the Old Bedford School property for $5.5 million.   PROJECT TOTAL $  70,000,000

           PROJECT COSTS        Thru                                                               FY 2025 to
          (amounts in 000s)    09/2019    FY 2020     FY 2021    FY 2022     FY 2023    FY 2024   Completion    Total
     Design                     421,580    7,978,420         -           -           -          -           -   8,400,000
     Land/Right-of-Way          705,364           -          -           -           -          -           -    705,364
     Construction                     -    6,500,000  45,500,000  3,415,784          -          -           -  55,415,784

     Landscaping                      -           -   1,500,000          -           -          -           -   1,500,000
     Equipment & Furnishings          -           -   2,250,000    250,000           -          -           -   2,500,000
     Other                      478,852     500,000     500,000                                                 1,478,852
           TOTAL COSTS          1,605,796  14,978,420  49,750,000  3,665,784         -          -           -   70,000,000
          SOURCE OF FUNDS       Thru                                                               FY 2025 to
          (amounts in 000s)    09/2019    FY 2020     FY 2021    FY 2022     FY 2023    FY 2024   Completion    Total
     Current Funds                    -           -          -           -           -          -           -          -

     GO Bonds Issued          60,000,000          -          -           -           -          -           -  60,000,000
     GO Bonds Unissued        10,000,000          -          -           -           -          -           -  10,000,000
     Certificates of Obligation       -           -          -           -           -          -           -          -
     Other                            -           -          -           -           -          -           -          -

     Unfunded                         -           -          -           -           -          -           -          -
           TOTAL COSTS         70,000,000         -           -          -           -          -           -   70,000,000
                        OPERATING BUDGET IMPACT
                                                                                   MAP/PHOTOGRAPH
         Will Impact                  Annual Cost/(Savings)
         Will Not Impact    Personnel   $
                            Operations  $
       # of Positions:      Capital     $
         Unable to quantify  Total      $
                          IMPACT EXPLANATION
     Once the building design is finalized, staffing levels will be
     evaluated and increased as appropriate. Utility costs are expected
     to increase for the new building, with offsets coming from the
     closure of existing facilities. The proposed fees will target 100% cost
     recovery of operational expenses.
         PROJECT SCHEDULE        START             FINISH
     Design                      FY17/18          FY 20/21
     Land/Right-of-Way          FY 18/19          FY 18/19
     Construction               FY 20/21          FY 21/22
     Finish Out                 FY 21/22          FY 21/22
     Other
                                                             376
          TOTAL SCHEDULE        FY 17/18          FY 21/22