Page 407 - City of Bedford FY20 Approved Budget
P. 407

CITY OF BEDFORD
                                                       CAPITAL PROJECTS
                                                           FY 2019-2020
         Funding Sources:
         (1) General Obligation Bonds  (4) Street Improvement E.D.C.  (10) PPF Contractual Obligation
         (2) Certificates of Obligation  (5) Water & Sewer Utility Repair Fund  (11) Cash
         (3)  Revenue Bonds   (6) Equipment Replacement Fund  (TBD) To Be Determined
                                             TOTAL EST. CURRENTLY                                                FUNDING
         PROJECT                               COST    FUNDED  FY 18/19  FY 19/20  FY 20/21  FY 21/22  FY 22/23  FY 23/24  SOURCE
         FACILITY ADDITIONS
      508 Animal Control Center Expansion        239,450  No                                                       1
      512 Fire/Police Combined Training Center   561,558  No                      561,558                          1
         Live Fire Training Building             290,000  No                      290,000                         TBD
         Second Story addition to Law Enforcement Center  TBD  No                                                 TBD
         City Hall                                TBD    No                                                       TBD
         Emergency Operations Center              TBD    No                         TBD                           TBD
         Fire Station 1 Relocation                TBD    No                         TBD                           TBD
         Fire Station 4                           TBD    No                         TBD                           TBD
         Fire Station 2 Renovation & Expansion    TBD    No                                  TBD                  TBD
         Fire Station 3 Renovation & Expansion    TBD    No                                  TBD                  TBD
         PARKS & RECREATION
         Phase Next                            70,000,000  Yes  1,605,795  14,978,420  49,750,000  3,665,785       1
         Fencing Replacement at Meadow Park & Stormie Jones  100,000  Yes  100,000                                 11
         Picnic Shade Structures                 50,000  Yes               50,000                                  11
         Protective Cover for Park Equipment     50,000  No                        50,000                         TBD
         Cheeksparger Trail                      800,000  No                      800,000                         TBD
         Park Storage Building                   600,000  No                               600,000                TBD
         WATER/WASTEWATER
           Cummings Elevated Storage Tank Painting & Interior Coating  2,100,000  No  300,000  1,800,000          TBD
           Simpson Terrace Elevated Storage Tank Painting  865,000  No    865,000                                 TBD
         SWIFT Water Main Replacements
           Automated Meter Reading             14,487,905  Yes  14,487,905                                         2
           Brown Trail - SH 183 to Goldhawk Lane  509,220  Yes   509,220                                           2
           Nottingham, Gregory and Bedford Addition  842,670  Yes  842,670                                         2
           Forest Ridge Drive - Harwood Road to Bedford Road  400,000  Yes  400,000                               2 & 5
           Forest Ridge Addition and Bell Manor Addition Units 3, 4   2,350,000  Yes  2,350,000                    2
           Briar Drive                           450,000  Yes             450,000                                  2
           Bedford Road - SH 183 to Somerset    1,955,000  Yes           1,955,000                                 2
      529  Stonegate North                       450,000  Yes             450,000                                  2
           Shady Brook Addition                 1,500,000  Yes           1,500,000                                 2
           Joiner Acres                         2,400,000  Yes           2,400,000                                 2
           McLain - Harwood to Oak Grove         485,000  Yes             485,000                                  2
           Harwood Road - Forest Ridge to Hurst City Limit  1,200,000  Yes       1,200,000                        2 & 5
           Bedford Rd 20" Transmission Line - EM Bilger to Forest
           Ridge                                 483,000  Yes                     483,000                          2
           Robindale Drive - Wade to Martha      156,000  Yes                     156,000                          2
           Deuce Drive - Tennis Drive to Brown Trail  144,000  Yes                144,000                          2
           Murphy Drive  - Harwood Road to Cheeksparger  1,610,000  Yes          1,610,000                         2
           Brown Trail - Bedford Road to Pipeline Road  2,000,000  Yes           2,000,000                         2
           Bedford Road - Central to SH 183     2,530,000  Yes                            2,530,000                2
           Wade - Pipeline to Donna              881,000  Yes                              881,000                 2
         New Water Main Installation
           Regents Park Area - Brown Trail to Somerset /Somerset
           Extension - Bedford Road to Somerset Circle / Shadywood
           Drive - Shadywood to Stonegate Drive North / Phyllis
           Extension - Ravenswood to Dora / Oakhurst Extention -
           Oakhurst to Tennis                   1,830,000  No                    1,830,000                        TBD
         Wastewater Rehabilitation
           Brown Trail - SH 183 to Bedford Road  578,333  Yes    578,333                                           2
      528  Kelmont Park Sewer Main Rehabilitaiton  673,500  Yes           673,500                                  2
           Bell Manor North Addition Sewer Main Rehabilitation  350,000  Yes  350,000                              2
           Harwood Terrace Addition Sewer Main Rehabilitation  410,000  Yes  410,000                               2
           Basin 19.1W - Warwickshire to SH 183  421,000  Yes             421,000                                  2
           Bell - Hurst                          241,000  Yes             241,000                                  2
           Oakwood Park East                     125,000  Yes             125,000                                  2
           Bedford Road - Somerset to Brown Trail  575,000  Yes           575,000                                  2
           Robindale Drive Sewer Main Rehabilitation - Wade to Martha  179,000  Yes  179,000                       2
           Deuce Drive Sewer Main Rehabilitation - Tennis Drive to
           Brown Trail                           170,200  Yes             170,200                                  2
           Murphy Drive Sewer Main Rehabilitation - Harwood Road to
           Cheeksparger                         1,725,000  Yes           1,725,000                                 2
           Joiner Acres                          550,000  Yes             550,000                                  5
                                                             374