                                           Goal 2: Improve Operational Efficiency
                                       Objective 1: Organize to Improve Operational Efficiency
                        Project                   Performance Measure(s)          City Service Team (Department)
             Core   Internal Engineering   Design 65,000 Linear Feet in FY 2019   Economic Development and Capital
             FED   Services for Water Utilities                                Investment (Water)
             2.1.2
             Summary:

             The City of Arlington Water Utilities has historically         Linear Feet Designed
             outsourced design phase services to private     70,000
             professional engineering firms.  It has been
             determined that utilizing internal engineering staff for   60,000
             design of specific projects would result in a lower   50,000
             design cost per foot of water and/or sanitary sewer   40,000
             lines.  In FY 2014, Water Utilities began performing
                                                             30,000
             design utilizing internal engineering staff.  The projects
             proposed for the internal design team consist of small   20,000
             diameter water and sanitary renewal projects.   10,000
                                                                  0
             Update:                                                 FY 2019  1st Qtr  2nd Qtr  3rd Qtr  4th Qtr
             The In‐House Design team has provided sealed plans       Total
                                     th
             for 23,355 linear feet in the 4  quarter. The total
             amount designed in FY 2019 is 65,166 linear feet.

                                      Financial/Economic Development

                                           Goal 2: Improve Operational Efficiency
                                       Objective 1: Organize to Improve Operational Efficiency
                        Project                   Performance Measure(s)          City Service Team (Department)
             Core   Non‐financial controllable    Reduce non‐financial controllable   Economic Development and Capital
             FED                           expenses by $1,000,000              Investment (Water)
             2.1.3
             Summary:

             The City of Arlington Water Utilities has an annual goal   Controllable Expense/Cost Reductions
             of reducing its non‐financial controllable expense   $1,000,000
             costs by $1,000,000.  The department will seek out
             various avenues to gain operational efficiencies.   $800,000

             Update:                                           $600,000
                       th
             During the 4  quarter of the fiscal year, the Water
                                                               $400,000
             Utilities department reduced its non‐financial
             controllable expenses by $255,350.                $200,000

                                                                     $0

                                                                         FY 2019 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr